Wedoany.com Report, On March 6, the announcement of successful bid candidates for the first section of the pile foundation project under the EPC contract for the Methanol-to-Olefins Unit (MTO, Olefin Separation, Butene-1, and Steam Cracking) of the 800,000 tons/year Coal-to-Olefins Project at Zhundong Wucaiwan, Xinjiang, operated by China Xinjiang Shaneng Chemical Co., Ltd., was published: Bid Announcement Image

First Section of Pile Foundation Project

First Successful Bid Candidate: Beijing Bosente Geotechnical Engineering Co., Ltd.

Bid Price: RMB 9,943,250.28

Other Project Winning Bid Information

Unit Area
Successful Bidder
MTO Unit EPC Turnkey Contract
Sinopec Engineering Incorporation (SEI)
Basic Design Services for Electrolytic Water Hydrogen Production Unit
China Wuhuan Engineering Co., Ltd.
Overall Design Institute, Overall Management Technical Services, Basic Design and Partial Detailed Design
China Tianchen Engineering Co., Ltd.
Basic Design for Purification Unit (Rectisol, Refrigeration, CCUS, Sulfur Recovery) and Methanol Synthesis Unit
China Wuhuan Engineering Co., Ltd.
Basic Design for Air Separation, Gasification and Shift Units
China Tianchen Engineering Co., Ltd.
Basic Design for Polypropylene Unit
Daqing Petrochemical Engineering Co., Ltd.
Air Separation Technology, Process Package, and Complete Equipment
PetroChina Jilin Chemical Engineering Co., Ltd.
Methanol Synthesis Technology Source and Process Package
Johnson Matthey

Xinjiang Shaneng Chemical Co., Ltd.

Zhundong Wucaiwan 800,000 Tons/Year Coal-to-Olefins Project

Project Name: Xinjiang Shaneng Chemical Co., Ltd. Zhundong Wucaiwan 800,000 Tons/Year Coal-to-Olefins Project

Project Owner: Xinjiang Shaneng Chemical Co., Ltd.

Construction Location: Modern Coal Chemical Industry Demonstration Zone, Zhundong Economic and Technological Development Zone, Xinjiang (West side of Shenqi Road, at the mine mouth of Wucaiwan No. 4 Open-pit Mine, Huoshaoshan Industrial Park, Wucaiwan Mining Area)

Total Project Investment: Total investment of RMB 20,858,011,900, of which environmental investment is RMB 1.667 billion, accounting for 8.0% of the project construction investment.

Construction Content: The project construction includes main engineering, storage and transportation engineering, public utilities, environmental protection engineering, and supporting projects. It mainly involves the construction of 13 production units, including: 3×75,000 Nm³/h oxygen air separation units (2 steam-driven, one electric-driven), 2.2 million t/a methanol unit (with gasification, shift & heat recovery, and purification for 657,000 Nm³/h effective gas (CO+H2)), 20,000 t/a sulfur recovery unit, 2.2 million t/a methanol-to-olefins unit, 800,000 t/a olefin separation unit, 50,000 t/a steam cracking unit, 15,000 t/a C4 to 1-butene unit, 450,000 t/a polypropylene (PP) unit, and 450,000 t/a polyethylene (PE) unit.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com