Vertex Minerals Sells 53 Ounces of Gold in April, Advances Underground Development at Reward Gold Mine in Australia
en.Wedoany.com Reported - Vertex Minerals sold 53 ounces of gold in April, while its Reward Gold Mine in New South Wales continued to advance underground development during the period. The company completed 78 meters of development and rehabilitated 42 meters of drives during the month, with an additional 32 ounces of gold on hand available for sale.
Monthly production declined compared to March, but the company stated this change was in line with the mine plan, primarily because all ore processed in April came from development headings, with no production contribution yet from airleg or jumbo level stopes.
Processing of ore from Decline No. 3 is expected to commence in early May, which is likely to accelerate the pace of mine production. Meanwhile, Vertex has initiated two new airleg stopes on the 671 and 677 levels, targeting the high-grade Paxtons lode.
Equipment upgrades are also progressively arriving. A second Aramine loader has been equipped with a remote control system and is now operating underground; the company has also ordered a Resemin MUKI LHBP narrow-vein longhole drill rig to improve blast hole drilling accuracy in small cross-section conditions; another Bird Machine underground truck is being urgently fitted out, and once operational, it will eliminate a key bottleneck in current material haulage.
Vertex anticipates that expanding production layouts across multiple mining areas and different levels will support underground production capacity. The scheduling plan is continuously optimized to increase production working faces throughout the mine's life. The company reiterated it remains on schedule to commence mining of the first longhole stope in October 2026.
Currently, restrictions on working hours and blasting times have been identified as the primary factors constraining available underground working hours. The Bathurst Regional Council is evaluating a development application amendment regarding working and blasting times for the Reward Gold Mine.
The Reward Gold Mine is part of Vertex's Hill End and Hargraves gold project, which covers multiple deposits with a total estimated Mineral Resource of 482,000 ounces at an average grade of 8.70 g/t.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com
Related Products

High-temperature Equal Wall Thickness High-power Screw Drilling Tool
Orient Energy & Technologies Co., Ltd.

Comprehensive Mining Automation Control System
Beijing Tianma Intelligent Control Technology Co., Ltd.
Linyi Steel Investment Special Steel 2.7 Million Tons per Year High-quality Special Steel Project
Capital Engineering & Research Incorporation Limited
Industrial and Commercial Point-Type Gas Detector
Jinan Benan Technology Development Co., Ltd.



Hydraulic Plate and Frame Filter Press
Guangdong Leimeng Intelligent Equipment Group Co., Ltd.

Core Technologies of the Mining Technology and Equipment Business Unit: Efficient Mining Methods and Processes
CHANGSHA INSTITUTE OF MINING RESEARCH CO., LTD.









