en.Wedoany.com Reported - The Lanzhou Chengguan District AI Industrial Park project, undertaken by Gansu Construction Investment Sixth Construction Company, is advancing the concrete pouring of 188 pile caps for Buildings 1 to 5. In recent days, the project team has broken down overall construction tasks into daily assignments and assigned responsibilities to individuals through scientific coordination and precise deployment, forming an efficient and focused work structure.

Located on the north side of Qingbaishi Street in Chengguan District, the project covers a total planned land area of 46,000 square meters, including five factory buildings, one equipment room, and outdoor supporting facilities and landscaping. Facing heavy construction tasks, tight schedules, and overlapping operations, the project team has defined phased construction goals, refined responsibilities for each position, and identified key construction milestones.

During construction, the project team has advanced various tasks according to the timeline. In April, the SDDC pile construction for the No. 6 equipment room and the earth backfilling for the No. 3 industrial factory building were initiated, marking the official start of foundation work. In May, construction progress accelerated comprehensively, with all pile integrity tests for the No. 2 industrial factory building passing inspection, and SDDC pile construction for the No. 6 equipment room, No. 3 industrial factory building, and surrounding areas fully completed. During the foundation phase, reinforcement binding for pile caps, foundations, and short column tie beams was carried out for the No. 2 industrial factory building, with all raw steel materials and mechanical connectors passing re-inspection, followed by pile cap concrete pouring and standardized curing. The No. 4 industrial factory building simultaneously commenced related reinforcement binding work, strictly implementing material re-inspection and process verification procedures. The No. 6 equipment room completed layered backfilling and compaction of 50 cm of cement-stabilized soil, laying the groundwork for subsequent main structure construction.
Currently, all construction tasks are progressing steadily, and the project team will continue with subsequent construction work.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com