Foundation Stone Laid for India's First Port-Based E-Methanol Plant, with a Total Investment of ₹23 Billion

2026-09-29 15:45
Favorite

en.Wedoany.com Reported - On September 26, the Deendayal Port Authority (DPA) of India and Assam Petro-Chemicals Limited (APCL) held a foundation stone laying ceremony for a 150 t/day e-methanol project at Kandla Port in Gujarat. The project has a total investment of ₹23 billion and adopts modular phased construction. Its feedstocks include renewable energy, water, and biogenic carbon dioxide, and its product is planned to supply ships on the Asia-Europe international trade routes.

India’s First Port-based e-Methanol Production Facility to Produce and Supply Green Fuel to Ships – EQ

Phase I is planned to build 50 t/day of e-methanol production capacity with an investment of ₹12 billion, targeting completion by January 2027; Phase II will add another 100 t/day of capacity with an investment of ₹11 billion, targeting completion by March 2027. After both phases are fully completed, the total capacity will reach 150 t/day.

DPA and APCL will make capital contributions in a 76:24 ratio. DPA will invest ₹5.6732 billion in equity funding and provide 75 acres of project land, desalinated water, and renewable energy supplied in the form of green hydrogen. APCL has included the Kandla 150 t/day e-methanol project in its subsequent construction plan.

The project adopts a process route that synthesizes methanol from green hydrogen and captured carbon dioxide. DPA had previously initiated early procurement of key equipment for the e-methanol project and in 2025 issued a call for expressions of interest for a Green Hydrogen Methanol Synthesizer, which is used to synthesize e-methanol from green hydrogen produced by electrolysis and captured carbon dioxide.

APCL had previously launched procurement for the preparation of a techno-economic feasibility report and a detailed project report for the Kandla Port e-methanol project. On January 29, 2026, APCL and DPA signed a memorandum of cooperation for the 150 t/day e-methanol project; on September 26, the project completed its foundation stone laying and entered the phased construction stage.

Kandla Port completed a shore-to-ship methanol bunkering trial on April 2, with participants including Stolt Tankers, J M Baxi, Aegis Vopak, Indian Oil, and DPA. The test covered fuel transfer, safety systems, and regulatory compliance. DPA plans to subsequently carry out ship-to-ship methanol bunkering and has proposed forming an e-methanol supply capacity of about 500,000 tonnes/year that meets RFNBO requirements by 2028–2029.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com