India's POWERGRID Wins Inter-State Transmission Project with Annual Transmission Fee of INR 4,306.7 Crore
en.Wedoany.com Reported - India's state-owned grid company POWERGRID has received a letter of intent for an inter-state transmission system project, under which it will build the "Lakadia Phase-II 7.5GW, Jam Khambhaliya Phase-II 5.5GW and Jamnagar Phase-I 1GW Common Transmission System Part-C" on a BOOT basis. The company's winning bid corresponds to an annual transmission fee of INR 4.3067 billion, with the project awarded through tariff-based competitive bidding (TBCB). POWERGRID disclosed the award to the Indian stock exchanges on September 26.

The core works of the project include the construction of a new 765/400/220kV Alephata substation in Maharashtra, equipped with two 1500MVA 765/400kV main transformers and three 500MVA 400/220kV main transformers, along with 765kV and 400kV lines, associated bays and reactive compensation equipment. The tender documents also specify an approximately 70 km 400kV double-circuit line from Alephata to Lonikand-I, as well as the looping-in and looping-out of the two 765kV lines from Aurangabad–Pune and Padghe–Pune into the Alephata station, with the associated LILO line length of approximately 20 km.
The system is intended to evacuate power from three renewable energy development zones in Gujarat: Lakadia, Jam Khambhaliya and Jamnagar. The planned evacuation capacities for the three locations are 7.5GW, 5.5GW and 1GW respectively, with Part-C mainly responsible for high-voltage transmission access from the western regional grid toward Maharashtra. India's Ministry of Power approved the implementation of the project through TBCB in February 2026 and designated PFC Consulting as the coordinating agency for the bidding process, while the project-specific company Lakadia C Power Transmission Limited had already been established.
According to the project tender documents, the main transmission facilities are planned to be completed within 36 months after the project's effective date. In addition to the new Alephata substation, the works also include six 765kV line bays, five 400kV main transformer bays, three 220kV main transformer bays, and 765kV and 400kV bus reactors and other equipment. After POWERGRID completes the takeover of the project company, the project will enter the detailed design, equipment procurement, line construction and substation construction stages.
This award is POWERGRID's ninth transmission system project secured through the TBCB mode so far in the 2026–2027 fiscal year, with the nine projects totaling an annual transmission fee of INR 76.6408 billion. Earlier in early September, the company also won the Barmer-II 6GW high-voltage direct current evacuation system in Rajasthan and the Lakadia Phase-II 7.5GW transmission project, while this Part-C corresponds to another independent inter-state transmission asset.
Related Products


1000kV Jin Southeast-Nanyang-Jingmen UHV AC Transmission and Transformation Pilot Demonstration Project
Anhui Hongyuan Steel Tower Co., Ltd.

220kV and Below Voltage Level Energy-saving Oil-immersed Power Transformers
FuZhou TianYu Electric Co., Ltd.
YE3 Series Low Voltage High Power Three-Phase Asynchronous Motor
Shandong Lijiu Electrical Machinery Co., Ltd.
714CD Series C-Band Weather Radar
Chengdu Zhongdian Jinjiang Information Industry Co., Ltd.
Aero Piston Engine - FF600 Two-Stroke Opposed Two-Cylinder Engine
China Times Prospect Science & Technology Co., Ltd.
Single-Phase Automatic Voltage Regulator(AVR)
Shaanxi Sefon Electrical Equipment Co.,Ltd.

Perfluorinated Ionic Membrane-CM-10N Series Membrane
Guizhou Juneng Century Technology Co., Ltd

Forest and Grassland Heat Source Infrared Monitor
China Huayun Meteorological Technology Group Co., Ltd.