Australia's Virya Receives Planning Permit for 1.3 GW Wind-Storage Project
en.Wedoany.com Reported - On November 2, Victoria's Minister for Planning Sonya Kilkenny approved the planning permit for the Meering West wind-storage project developed by Virya Energy. Located in northern Victoria, the project has a planned wind capacity of 1.3 GW, with up to 155 wind turbines and a co-located 500 MW/1000 MWh battery energy storage system, representing a total investment of approximately AUD 2 billion. Construction is planned to begin in 2029 and be completed in 2031.

The Meering West project is located approximately 25 kilometers southwest of Kerang in Victoria, with a maximum turbine design height of 280 meters. The project includes a centralized battery energy storage facility, and the development plan reserves two candidate storage sites, with only one ultimately selected for construction. The specific technical configuration of the storage facility will be determined during the detailed design phase.
The project is planned for direct connection to the proposed VNI West interstate transmission line, which is planned to cross the Meering West project area. Virya Energy had previously developed an alternative transmission plan connecting to the grid via Kerang, and should VNI West be cancelled, the developer would revert to that connection route. Following approval of the planning permit, the project still requires environmental approval under Australia's Environment Protection and Biodiversity Conservation Act.
The planning application for the Meering West project was submitted to Victoria's Department of Transport and Planning on July 6, 2025, and entered a 28-day public exhibition process in July 2026. The review received 108 public submissions, of which 102 opposed the project, and the Gannawarra local government also raised objections. The Victorian government ultimately approved the project's state-level planning permit before the caretaker government period began ahead of the November state election.
According to the construction schedule published by the project developer, construction preparation, subsequent approvals, and early works will proceed from 2027 to 2028, with main construction scheduled from 2029 to 2031 and operations planned to begin in 2032.
Related Products

KYN28 - High Voltage Switchgear
Anhui Tianying Electrical Equipment Manufacturing Co., Ltd.




Environmentally Friendly Flame-retardant PVC Double-layer Insulated Wire
Sichuan Chndo Cable Co., Ltd.

Post-type AC Pollution-resistant Disc Suspension Porcelain Insulator (Triple Umbrella Type)
Shandong High Voltage Insulator Co., Ltd.


Pneumatic high-pressure wear-resistant ball valve
Zhejiang Deca Control Valve Meter Co., Ltd.