Michigan Advances Restoration of Four Dams and Lake Recovery
en.Wedoany.com Reported - On November 4, the Four Lakes Task Force in Michigan, USA, released the latest progress on the restoration projects of four dams: Sanford, Secord, Smallwood, and Edenville. Currently, the Sanford Dam has completed its main restoration, the Smallwood Dam has entered the project closeout phase, the Secord Dam is expected to reach the conditions for completion of the main works in November 2026, and the Edenville Dam is scheduled to complete the main works in September 2027. The restoration of the four dams and the refilling of the lakes will be advanced in phases, with Secord Lake expected to resume impoundment in spring 2027 and Wixom Lake expected to resume impoundment in spring 2028.

The Sanford Dam currently has no ongoing main construction activities, and the reservoir has been restored to the legal summer water level. The Smallwood Dam also reached the legal summer water level on October 5, 2026, and construction crews are working through the remaining punch list, including adjustments to gates and seals, site grading, and surface restoration. The contractor previously estimated that most closeout work would be completed in October, after which construction equipment and temporary facilities would be gradually demobilized.
The Secord Dam is still undergoing main restoration. The works mainly involve the construction of the spillway, low-level outlet facilities, and gate systems. One set of gates was previously sent back to the manufacturer for repair due to quality issues, with the manufacturer bearing the related repair costs; however, the Four Lakes Task Force still had to bear the resulting engineering and technical costs and adjust the affected construction schedule. The dam is currently expected to reach the conditions for completion of the main works in November 2026, and Secord Lake is planned to begin refilling in spring 2027.
The Edenville Dam is the longest-duration project among the four restoration projects. Construction continues on the spillways on both river sides, the control structures, and related concrete structures, while water flow diversion in the construction area also needs to be arranged. According to the schedule published by the task force in October 2026, the project is expected to reach the conditions for completion of the main works in September 2027, after which impoundment of Wixom Lake is planned to begin in spring 2028.
Related Products

Bidirectional Metal Hard Sealed Seawater Butterfly Valve
Henan Quanshun Flow Control Science & Technology Co., Ltd.

145kV Porcelain Column Type Sulfur Hexafluoride Circuit Breaker
TBEA ZONFA Shanghai High Voltage Switchgear Co., Ltd.



CITIC Heavy Industries Tunneling Equipment Tunnel Engineering Shield Machine
CITIC Heavy Industries Co., Ltd.



Industrial and Commercial Point-Type Gas Detector
Jinan Benan Technology Development Co., Ltd.