en.Wedoany.com Reported - The Operation Village project of the Pha Lai Hydropower Station, located on the right bank of the Mekong River in Laos, is accelerating construction and has entered the peak period of interior finishing work overall. As a core supporting project for the Pha Lai Hydropower Station, this project undertakes the crucial functions of providing office space and living facilities for the station's staff, playing a key role in ensuring the long-term safe and stable operation of the power station and improving the work and living quality of the on-site personnel.
The Operation Village has a planned construction area of approximately 7,301 square meters, divided into two main camps, with a total building area of 21,708 square meters. The project primarily involves constructing office buildings, dormitories, canteens, a sports center, and ancillary facilities. It also includes supporting infrastructure such as gates, perimeter walls, site landscaping, and various pipeline networks to comprehensively meet the operational needs of the power station. Currently, interior work including wall and floor finishing, door and window installation, and final electrical and plumbing installations in each building is fully underway. Simultaneously, outdoor water supply and drainage, power (both strong and weak current), fire protection pipeline networks, and site road works are also progressing.
During the construction process, the project department adheres to the principles of "setting examples and implementing closed-loop management," conducting full-process on-site supervision for key procedures such as rebar tying, concrete pouring, and waterproofing work. The department strictly enforces the rule that "the next phase of work cannot begin until the previous one passes inspection," maintaining rigorous control over construction details. Furthermore, the department strictly controls the quality of raw materials, implementing a "inspect before use" system. All construction materials undergo comprehensive verification and random sampling for testing, establishing a complete quality traceability system. Construction techniques are also optimized to enhance building durability and safety.
To date, the acceptance qualification rate for all sub-projects and individual components of the Pha Lai Hydropower Station Operation Village Project has reached 100%, receiving high recognition from the client and supervision parties. The project department stated that it will continue to uphold its commitment to quality, advancing the finishing and supporting works with stricter standards and more substantial measures, striving to build a high-quality demonstration project and providing a solid guarantee for the efficient operation and maintenance of the Pha Lai Hydropower Station.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com