DP World of the UAE Advances Pakistan Rail Freight Corridor and Multimodal Logistics Park Construction
en.Wedoany.com Reported - On November 20, Fakhr Alam, Vice Chairman and Executive Vice President of DP World Pakistan, the UAE port and logistics operator, said in an interview that the dedicated freight rail corridor from Karachi Port to Pipri in Pakistan is planned to commence operations by the end of 2026. The project is being advanced through cooperation among DP World, Pakistan Railways, and the National Logistics Corporation (NLC). The first phase includes upgrading approximately 50–52 kilometers of existing railway from Karachi Port to the Pipri marshalling yard and building a multimodal logistics park. Subsequent phases will also include expanding to double-track railway and port logistics facilities.

The project adopts a phased construction model. The first phase mainly involves upgrading existing railway lines and building the Pipri multimodal logistics park to provide warehousing, container handling, cargo consolidation and deconsolidation, and cargo distribution services. After imported containers arrive at Karachi Port, they will be transported by rail to Pipri and then transferred to road or rail transport depending on the destination; export cargo will follow the reverse process to reach the port for shipment. This model connects port container collection and distribution with inland logistics nodes, reducing the need for freight vehicles to pass through Karachi's urban areas.
According to Pakistan Railways documents, as of October 2026, approximately 2.5 kilometers of track had been laid, while the logistics park office buildings, supporting facilities, and loading and unloading platforms were still under construction. The first phase plans to operate 2 freight trains per day, and the subsequent second phase is intended to build new double-track railway, with preliminary planning to increase transport capacity to 17 trains per day. The logistics park land area will also expand from approximately 25 acres in the first phase to approximately 500 acres in the second phase, equivalent to about 202 hectares.
The first-phase project investment is approximately USD 20 million (approximately RMB 134 million), of which NLC bears USD 17 million and Pakistan Railways bears USD 3 million. NLC funds are mainly used to build the multimodal logistics park and purchase rolling stock and cargo handling equipment; Pakistan Railways funds are used for line safety upgrades, including track, signaling, and electrical works. The estimated investment for the second-phase project is approximately USD 410 million (approximately RMB 2.74 billion).
The broader investment plan announced by DP World this time is approximately USD 500 million (approximately RMB 3.34 billion), covering the 52-kilometer railway, the upgrade of Qasim International Container Terminal, and the expansion of inland logistics operations. The multi-phase foreign direct investment scale previously announced by NLC was USD 400 million.
Before the project was built, cargo transport at Karachi Port relied heavily on roads. According to assessment materials from Pakistan Railways, in fiscal year 2023–2024, approximately 17,000 freight trucks entered and exited Karachi Port each day, and port cargo transport was mainly completed by road, with low railway freight utilization. Freight trucks were also subject to a daily traffic restriction from 23:00 to 6:00 the next day. Once the rail corridor is completed, container transport between the port and inland marshalling yards will gain an additional rail transport option, easing road traffic pressure around the port area.
The project cooperation framework was established by Pakistan and the UAE in January 2024. The two sides signed a term sheet for project implementation in January 2025, signed the first-phase commercial agreement in September 2025, and held a groundbreaking ceremony in January 2026. The initially announced first-phase construction target was completion within 4 months after groundbreaking, while the latest operational target has been adjusted to the end of 2026.
Related Products

GSR6-27.5kV SF6 Free Gas-insulated Metal-enclosed Switchgear
Zhejiang Juhonkia Intelligent Electric Co., Ltd.
China - Alashankou/Khorgos - Europe Full Range Transportation (Mala/Hamburg/Duisburg/Budapest, etc.)
Shenzhen Neptune Logistics Co., Ltd.
![IVECO Cash-in-Transit [DMT5048XYCL3-AM] - Chongqing Dima Industry Co., Ltd](https://img.wedoany.com/2026/0911/20260911030157582.png)





NTE150 Electric Drive Mining Dump Truck
Inner Mongolia North Heavy Industries Group Co., Ltd.


CLW5180TXSD6 Dongfeng Tianjin Washing and Sweeping Truck
ChengLi Special Automobile Co., Ltd.