First 120-Meter Berth of Mindanao Container Terminal in the Philippines Scheduled for Completion in Q1 2027
en.Wedoany.com Reported - On November 25, International Container Terminal Services, Inc. (ICTSI) of the Philippines disclosed that the 300-meter berth extension project at its Mindanao Container Terminal (MCT) is progressing as planned, with the first 120-meter section expected to be completed by the end of the first quarter of 2027. The entire expansion phase is scheduled for completion in the first quarter of 2028, at which point the full 300-meter berth extension will be finished and three newly ordered post-Panamax quay cranes will be put into operation.

The project is located in the PHIVIDEC Industrial Estate in Tagoloan, Misamis Oriental, Philippines, and is operated by Mindanao International Container Terminal Services, Inc. (MICTSI). The terminal is the primary international container shipping gateway for the Northern Mindanao region of the Philippines, handling regional import and export cargo loading and unloading as well as international shipping connections.
The berth expansion is being implemented in phases. The first 120-meter section is scheduled for completion by the end of the first quarter of 2027, at which time the terminal's total operational berth length will reach 420 meters, providing space for increased vessel calls and shipping services. The first newly ordered post-Panamax quay crane is expected to arrive shortly after the completion of the first berth section and will be put into service after installation and commissioning, with the remaining two to be delivered in subsequent phases of the project.
In addition to the berth and quay crane equipment, the expansion project also includes expansion of refrigerated container facilities, expansion of the empty container yard, and enhancement of container storage capacity. The terminal is constructing a new substation to provide power supply for the additional handling equipment and future operational needs. These facilities will collectively improve the terminal's vessel handling, cold-chain cargo processing, and yard turnover capabilities.
The project's construction plan was formally confirmed in 2024, when MICTSI announced an investment of over USD 100 million (approximately RMB 710 million) for infrastructure upgrades and cargo handling equipment procurement, including the 300-meter berth extension and equipment renewal. The company also obtained an additional 25-year management and operating concession for MCT.
The terminal has already received four hybrid rubber-tyred gantry cranes (RTGs), which arrived approximately three months ahead of schedule. These units will be used for container yard handling operations and, together with the new quay cranes and yard facilities, will form the handling capacity upgrade system for this expansion.
Aurelio Garcia, Chief Executive Officer of MCT, stated that as the new berth capacity is gradually phased in starting in 2027, the terminal will be able to accommodate more vessel calls and support additional shipping services. Under the current plan, the full expansion phase will conclude in the first quarter of 2028.
Related Products




One-Stop Steward Service for the Entire Logistics System Integration Chain
Zhongding Intelligent (Wuxi) Technology Co., Ltd.


XC-6000e Type Aviation Catering Truck (Fuel Type)
Shenzhen CIMC-TianDa Airport Support Ltd.![IVECO Cash-in-Transit [DMT5048XYCL3-AM] - Chongqing Dima Industry Co., Ltd](https://img.wedoany.com/2026/0911/20260911030157582.png)

GSR6-27.5kV SF6 Free Gas-insulated Metal-enclosed Switchgear
Zhejiang Juhonkia Intelligent Electric Co., Ltd.