Eletronuclear Cost-Savings, Plans for Angra 3 Operation in 2031
2025-02-11 16:14
Favorite

Angra 3 is currently about 65% complete


Wedoany.com Report-Feb 11, Brazil's nuclear power plant operator Eletronuclear has announced cost-saving measures which it says are aimed at improving the current governance model and enabling the continuation of strategic projects such as Angra 3.

Brazil has two operating reactors - Angra 1 and Angra 2 - which generate about 3% of the country’s electricity. Work on the Angra 3 project - to feature a Siemens/KWU 1405 MW pressurised water reactor - began in 1984 but was suspended two years later, before construction began. The scheme was resurrected in 2006, with first concrete in 2010. However, amid a corruption probe into government contracts, construction of the unit was halted for a second time in 2015, when it was 65% complete.

The project resumed again in November 2022 - at the time of the project's revitalisation, Eletronuclear's aim was to start operations by the end of 2026. However, work halted again in April 2023 after disputes with the municipality of the City of Angra dos Reis over agreements relating to "environmental compensation" payments and also changes relating to the granted planning permission.

The company is currently awaiting a government decision on completing Angra 3 - it said in September that a study by Brazil's National Bank for Economic and Social Development had concluded that the cost of abandoning construction of the part-built nuclear power unit could be about BRL21 billion (USD3.7 billion), which it says was about the same as the cost of completing it.

It says the unit's generating capacity will be sufficient to supply 4.5 million inhabitants and would also create around 7000 direct jobs at its peak, in addition to a much larger number of indirect jobs. It also noted that about BRL800 million in Angra 3 equipment was used in Angra 2 and between BRL500-600 million in nuclear fuel, which had been initially purchased for Angra 3, had been used in Angra 2.

Eletronuclear says its restructuring plan was approved by the board at the end of January and will come into effect on 1 April. It will reduce management levels and end overlapping activities, with management positions cut from 116 to 73. The changes are together said to be likely to bring annual savings of about BRL 3 million.

In its announcement, the company says it aims to reduce spending on materials and third party services - by reviewing contracts, and ensuring optimisation of processes - to help improve the economic viability of the company and strategic projects such as Angra 3.

It said "the new organisational chart is in line with the current stage of the Angra 3 project. Previous planning predicted the plant would be completed in 2028, but with the new estimates, it is expected to start operating in 2031. In this way, the new format allows for better use of labour, reallocating employees who were focused on the unit's operations and engineering services to the two plants in operation (Angra 1 and 2)".

Raul Lycurgo, president of Eletronuclear, said: "This organisational reformulation allows for a leaner and more efficient model, aligned with good sector practices, without compromising the safety and quality of the services provided."

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com
Related Recommendations
2026 China's Local Blueprint: Shanghai, Sichuan, Hubei, Anhui, and Other Regions Include Fusion Energy Projects in Their 2026 Key Project Lists
2026-03-19
China Nuclear Environmental Protection: Concentrating Efforts on Reform for Breakthrough, Striving to Create a New Situation in the Nuclear Environmental Protection Industry
2026-03-19
Fu Liangqian Appointed as Vice President of the Southwestern Institute of Physics (SWIP) under China National Nuclear Corporation
2026-03-19
China Nuclear Power Equipment Holds Kick-off Meeting for the Promotion and Implementation of the "1455" Project
2026-03-19
Zhu Xiaoyan, Member of the Party Leadership Group and Deputy Director of the East China Energy Regulatory Bureau: Seizing Opportunities, Striving Diligently to Contribute East China Energy Regulatory Strength to Building a Strong Energy Nation
2026-03-19
CGNPC Environmental Protection Party Committee Deputy Secretary and General Manager Ren Junhua Meets with Southwest University of Science and Technology Vice President Fa Tao and Delegation
2026-03-19
China National Nuclear Power 5th Construction Company Selected as a National Intellectual Property Demonstration Enterprise
2026-03-19
2026 China-Korea Nuclear Energy Industry Exchange Seminar Concludes Successfully in Qingdao — Focusing on Supply Chain Collaboration and Overseas Expansion, Discussing New Opportunities for China-Korea Nuclear Energy Cooperation
2026-03-19
China's First Domestically Developed "Hualong One" Main Steam Release Isolation Valve Successfully Shipped to Guangdong Lufeng Nuclear Power Plant
2026-03-19
Taiwan Power Company of China Plans to Submit Reactivation Plan for Third Nuclear Power Plant in March; Potential Restart in 2028 After Safety Review Approval
2026-03-19
Lastest Bulletin
1
Inyanga Marine Energy Group welcomes the Welsh Government’s Renewable Energy Sector Deal.
2
2026 China's Local Blueprint: Shanghai, Sichuan, Hubei, Anhui, and Other Regions Include Fusion Energy Projects in Their 2026 Key Project Lists
3
China Nuclear Environmental Protection: Concentrating Efforts on Reform for Breakthrough, Striving to Create a New Situation in the Nuclear Environmental Protection Industry
4
Fu Liangqian Appointed as Vice President of the Southwestern Institute of Physics (SWIP) under China National Nuclear Corporation
5
China Nuclear Power Equipment Holds Kick-off Meeting for the Promotion and Implementation of the "1455" Project
6
Zhu Xiaoyan, Member of the Party Leadership Group and Deputy Director of the East China Energy Regulatory Bureau: Seizing Opportunities, Striving Diligently to Contribute East China Energy Regulatory Strength to Building a Strong Energy Nation
7
CGNPC Environmental Protection Party Committee Deputy Secretary and General Manager Ren Junhua Meets with Southwest University of Science and Technology Vice President Fa Tao and Delegation
8
China National Nuclear Power 5th Construction Company Selected as a National Intellectual Property Demonstration Enterprise
9
2026 China-Korea Nuclear Energy Industry Exchange Seminar Concludes Successfully in Qingdao — Focusing on Supply Chain Collaboration and Overseas Expansion, Discussing New Opportunities for China-Korea Nuclear Energy Cooperation
10
China's First Domestically Developed "Hualong One" Main Steam Release Isolation Valve Successfully Shipped to Guangdong Lufeng Nuclear Power Plant