en.Wedoany.com Reported - Danish infrastructure investor Copenhagen Infrastructure Partners has reached financial close for the Pestera II onshore wind farm project in Romania. The 392 MW wind farm, located in Constanța County, Romania, has a project financing scale of approximately €510 million and is expected to enter commercial operation in 2028.

The Pestera II wind farm project is held by the CIP Growth Markets Fund II, with the European Investment Bank and a Danish pension fund brought in as co-investors. Project financing is provided by seven banks, including Erste Bank, Banca Comerciala Romana, Deutsche Bank, Societe Generale, BRD, Eurobank, and Piraeus Bank. A 245 MW capacity of the project secured a 15-year Contract for Difference in December 2024.

The wind farm will install 56 Nordex N163-6.X series wind turbines, each with a rated capacity of 7 MW. Romanian contractor Electrogrup will be responsible for the balance of plant works, while Blue Power Partners will provide construction management services. With the financial close of the 392 MW Pestera II wind farm project, the subsequent implementation phases for wind turbines, on-site roads, collection lines, substations, and grid connection works in Romania will proceed.

This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com