Krasnoyarsk CHPP-3 in Russia Advances Replacement of 15-Ton Boiler Heating Surfaces

2026-10-21 09:10
Favorite

en.Wedoany.com Reported - On October 19, Russia's Siberian Generating Company announced progress on the 2026 equipment maintenance program at Krasnoyarsk CHPP-3. The plant has completed maintenance on 7 main equipment units of Unit 1 and has carried out repairs on 3 hot-water boilers and steam boilers No. 4 and No. 5. The plant is currently completing maintenance on the No. 1 KV-TK-100 hot-water boiler, which involves replacing 15 tons of boiler heating surfaces.

This round of maintenance at the plant also includes boiler, turbine and generator-related equipment, as well as the replacement of large-diameter valves in the plant's piping systems. According to the annual plan, technicians will carry out maintenance on steam boiler No. 3 in the fourth quarter. The plant is responsible for centralized heat supply to the Sovetsky District and Pokrovsky residential area of Krasnoyarsk.

Unit 2 of Krasnoyarsk CHPP-3 was commissioned in December 2025, adding 185 MW of electrical capacity and 270 Gcal per hour of heat supply capacity. In the first 8 months of 2026, the plant generated a total of 853 million kWh, up 54% year on year.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com