en.Wedoany.com Reported - On November 19, the Los Angeles County Metropolitan Transportation Authority (Metro) plans to consider awarding a light rail track fastener replacement contract to Balfour Beatty Infrastructure in the amount of $13.6837 million (approximately RMB 97.2 million), with a contract term of 3 years. The project covers the Metro C Line and the southern segment of the K Line, totaling approximately 19.3 miles (31.1 kilometers), and primarily involves the removal and replacement of 53,530 existing direct fixation track fasteners. The contract is currently under committee review.

This project is part of Metro's capital asset renewal program, focusing on the first-generation direct fixation track fasteners on the C Line and the southern segment of the K Line that have been in service for more than 30 years. These fasteners were manufactured by LORD Corporation and were installed during the original construction of the C Line. They have been in continuous service since the line entered commercial operation in 1995, with an original design service life of 25 to 30 years. Due to long-term exposure to the coastal environment, train operating loads, and temperature and humidity variations, some fasteners have exhibited wear and cracking.

Direct fixation fasteners are critical connection components of ballastless track, directly securing the rail to the concrete track foundation while performing functions such as maintaining gauge, restricting rail displacement, reducing vibration, and providing electrical insulation. Fastener failure can cause rail misalignment and affect train operating safety. Currently, Metro primarily maintains line conditions through routine inspections and fault-based replacements, but localized repairs require measures such as single-track operation or train speed reductions, which can cause operational disruptions. Therefore, Metro has decided to carry out concentrated replacement on the affected lines rather than continuing to rely on scattered repairs to address aging issues.

The project plans to remove 53,530 first-generation fasteners and install improved new fasteners. The new fasteners are designed for durability in the coastal operating environment of the South Bay area and the Interstate 105 corridor, which consists primarily of elevated and at-grade alignments, with an expected service life of 30 to 35 years. The scope of work covers the renewal of the fastener system between the rail and the track support structure, and the related works must be coordinated with track maintenance, construction organization, and line operations scheduling.

The contract budget is $13.6837 million, structured as a three-year firm fixed-price contract, and is planned to be implemented by Balfour Beatty Infrastructure. Meanwhile, Metro plans to increase the project's total lifecycle budget by $4.0655 million, raising the total budget from $17.1 million to $21.1655 million. The budget increase is primarily intended to cover labor costs, engineering design, project management, and contingency reserves for key material price fluctuations. Project funding comes from local sources, with $1.5404 million already programmed in Fiscal Year 2027, and the remaining funds to be secured in subsequent fiscal year budgets.

This replacement project is an existing line condition maintenance project and does not involve new track construction. The C Line and the southern segment of the K Line connect Redondo Beach and Norwalk, passing through communities including Norwalk, Downey, Paramount, Lynwood, Hawthorne, and Torrance, and interfacing with multiple bus and rail lines. Upon completion of the comprehensive fastener renewal, it is expected to reduce temporary repairs and speed restrictions caused by fastener fatigue and damage, thereby improving line operating reliability.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com