Canada's Vizsla Silver Delays First Silver Production at Mexican Mine to 2028

2026-11-20 09:17
Favorite

en.Wedoany.com Reported - On November 19, Canadian mining company Vizsla Silver pushed back the target for first silver production at its Panuco silver-gold project in Sinaloa, Mexico, from the second half of 2027 to the second half of 2028. The revised development timeline takes into account project permitting, site restart preparations and construction progress. The project is wholly owned by Vizsla Silver, and the company is coordinating on-site security measures with Mexican federal authorities in preparation for a phased resumption of mining operations.

Engineering design and equipment procurement for the Panuco project continue to advance. M3 Engineering & Technology has completed approximately 50% of the engineering design work, and about 85% of the equipment required for the planned processing plant has been ordered. The project has previously awarded three major contracts covering engineering, procurement and construction management (EPCM), mine design and equipment supply, with the main mining contract expected to be awarded in the next phase.

The site restart plan involves new security facilities, on-site support measures and an independent third-party security risk assessment. Vizsla Silver is working with Mexican federal agencies and specialized security consultants to improve on-site safety conditions. The company will determine the timing and scope of a phased return to site based on security conditions and the readiness of personnel and facilities.

According to the feasibility study completed in November 2025, the Panuco project has an initial ore processing capacity of 3,300 tonnes per day, with plans to increase to 4,000 tonnes per day in the fourth year of production. The initial mine life is 9.4 years, with average annual silver equivalent production estimated at 17.4 million ounces and average annual production of 20.1 million ounces over the first five years. The project's initial capital investment is estimated at US$238.7 million, and a formal production decision remains subject to completion of detailed engineering design, financing arrangements and required permit approvals.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com