Design of Taiwan, China 495 MW Offshore Wind Foundations Verified
en.Wedoany.com Reported - On November 23, DNV (Det Norske Veritas) announced the design evaluation results for the wind turbine support structures of the 495 MW Formosa 4 offshore wind project in Taiwan, China, and confirmed that it has issued a design evaluation conformity statement, verifying that the relevant designs meet applicable international and local standards as well as project-specific technical requirements. The project developer, Synera Renewable Energy, had announced the receipt of this statement on October 30.

The project is located 18 to 20 kilometers off the coast of Miaoli County, with water depths of 57 to 64 meters at the site. It adopts a three-legged jacket foundation design, with each foundation averaging 91 meters in height, a maximum base span of 35 meters, and a weight of approximately 2,500 tonnes. The piles securing the jackets are designed with lengths of 80 to 101 meters. DNV conducted an independent review of metocean data, seabed geology, and environmental loads, confirming that the support structure design strength can withstand typhoon, seismic, and wave loads in the Taiwan Strait.
The project plans to install 35 Siemens Gamesa 14 MW offshore wind turbines, with nacelles supplied from its Taichung manufacturing base. Under the engineering contracts signed in 2025, Century Wind Power is responsible for the supply and supply chain coordination of 35 jacket foundations, while CDWE (CSBC-DEME Wind Engineering) is responsible for the transportation and installation of wind turbine foundations and the offshore substation, as well as seabed scour protection works. Offshore foundation installation was originally scheduled to commence in early 2027 using the Green Jade heavy-lift installation vessel.
The project's offshore substation is being delivered under an EPC contract by a consortium comprising Semco Maritime and PTSC Mechanical & Construction, with steel structure fabrication commencing at its Vietnam manufacturing base in January 2026, and delivery planned for the end of 2027.
The project completed the power sales arrangements for its full installed capacity through three corporate power purchase agreements in December 2025. According to the construction plan announced by Synera Renewable Energy, the project will be completed and grid-connected in 2028, with an expected annual power generation of approximately 2 billion kWh.
Related Products



Photovoltaic and Wind Power Generation Technology
Beijing Boqi Electric Power SCI-TECH Co., Ltd.





Hydraulic Turbine Genset
Dongfang Electric Corporation Dongfang Electric Machinery Co., Ltd.
Optional Accessory - Auxiliary Sampling Module
Beijing Soaring Electric Technology Co., Ltd.
