Ukraine's Autostrada Completes Tunnel Construction Beneath European Union Avenue for Kyiv Metro

2026-11-25 16:37
Favorite

en.Wedoany.com Reported - On November 23, Ukrainian engineering contractor Autostrada disclosed that the main construction of the double-deck running tunnel beneath European Union Avenue as part of the Kyiv Metro Vynohradar extension project has been completed. The construction team is currently carrying out underground utility construction and road restoration, with approximately 80% of the planned works for the relevant road section completed. The contractor plans to restore road traffic before Christmas 2026.

The project is part of the extension of the Kyiv Metro Syretsko-Pecherska Line toward the Vynohradar residential area, with a total length of approximately 3.78 km. It includes the planned construction of Mostytska Station and Varshavska Station, as well as a branch line leading to the future Vynohradar Station. The construction section beneath European Union Avenue is located between the future Varshavska Station and Mostytska Station and adopts the cut-and-cover method to build a double-deck monolithic concrete running tunnel, which differs from the section between Syrets Station and Mostytska Station constructed using the shield tunneling method.

After completion of the main tunnel structure, the site is still carrying out construction of stormwater drainage networks, domestic sewage networks, and drainage systems, while simultaneously relocating water supply, heating, gas pipelines of various pressure levels, high-voltage power cables, and communication lines. In areas where underground utility relocation has been completed, road and sidewalk restoration has begun, including milling of old asphalt pavement and replacement of road structural base layers.

The supporting main stormwater pipeline is constructed using microtunneling technology, implemented by NIKA microtunneling equipment. As of November 23, 460 meters of the designed length of 750 meters have been completed, with approximately 290 meters remaining. This work is being advanced in parallel with the metro tunnel construction and involves comprehensive upgrading of underground drainage facilities and the existing municipal utility system.

Meanwhile, Autostrada is assembling a new tunnel boring machine named "Viktoria." More than 70% of the new equipment, manufactured by Germany's Herrenknecht, has arrived at the site. After assembly and commissioning, it will be used for boring the left-line tunnel between Syrets Station and Mostytska Station. The equipment represents an investment of more than EUR 15 million. Previously, Autostrada conducted a technical inspection of the existing "Galyna" tunnel boring machine and found that approximately 99% of the equipment was unsuitable for continued use, and therefore decided to purchase new equipment as a replacement.

According to information previously published by the Kyiv Metro, the first-phase contract for the Vynohradar extension project was signed on August 14, 2024, with a contract value of approximately UAH 13.8 billion. The scope of works includes the section from Syrets Station to Varshavska Station, as well as part of the branch line toward Vynohradar. Project implementation is also affected by factors such as municipal financial arrangements, construction conditions, and the local security environment.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com