Public consultation concludes for 90 MW data center south of Paris, France
en.Wedoany.com Reported - On November 25, the three-month public consultation concluded for a data center project developed by SNC PARAY DC, a subsidiary of Hines, in Paray-Vieille-Poste, Essonne, France. The project is located in the industrial zone around Paris Orly Airport, covers an area of 29,655 square meters, and has a planned total power capacity of approximately 90 MW. The public consultation involved two major administrative approval procedures: environmental permit and construction permit. The project is scheduled for delivery in 2031.

According to the engineering plan published by the local municipal council, the project will involve renovation and construction at the former pilot training center site of Air France. The main data center building is planned as a three-story structure with a total floor area of approximately 23,000 square meters, of which 16,000 square meters will be used for cloud computing data storage and public digital infrastructure equipment rooms, and 7,000 square meters for technical equipment facilities. The project will also include supporting construction of a high-voltage substation, medium-voltage power distribution facilities, emergency power generation facilities, logistics facilities, and a waste heat utilization building.
As the site was previously used for industrial production over a long period, the soil and groundwater have been affected by pollutants such as organic solvents and paints. The project will therefore involve demolition of existing buildings and a site contamination remediation project lasting approximately two years. An integrated business service facility of approximately 3,000 square meters is also planned for training, office, and commercial support services.
In terms of energy and environmental engineering, the project plans to connect to the Rungis power system of RTE, France's transmission system operator, via a 225 kV grid starting from 2031. The data center is designed with a target Power Usage Effectiveness (PUE) of 1.22, will adopt a closed-loop cooling system, and plans to install rooftop photovoltaic facilities. The project is applying for BREEAM and HQE green building certifications.
The project intends to supply waste heat generated by servers to the planned district heating network in Thiais, while also meeting the heating needs of the supporting business facilities. The relevant waste heat utilization research agreement was signed at the end of 2025. The site's permeable area ratio will increase from 14% to 36%.
On October 12, the Paray-Vieille-Poste municipal council approved a conditional support opinion for the project with 26 votes in favor, requiring the project to meet urban planning, environmental protection, and technical review requirements of all relevant agencies, and to incorporate the data center into the local emergency management system. The investigating commissioner responsible for the public consultation will submit the investigation report and review opinion within three weeks after the conclusion of the consultation.