STRABAG Consortium Launches Replacement of the North Elbe Bridge on the A1 Motorway in Hamburg, Germany

2026-11-27 17:00
Favorite

en.Wedoany.com Reported - On November 23, a groundbreaking ceremony was held for the replacement of the North Elbe Bridge in Hamburg, Germany. Die Autobahn GmbH des Bundes commissioned the German Federal Highway Planning and Construction Company (DEGES) to organize and implement the project, and a consortium comprising STRABAG, ZÜBLIN, MCE GmbH and Victor Buyck Steel Construction is responsible for the construction of the first replacement bridge. The first-phase construction contract is worth approximately EUR 150 million (approximately RMB 1.23 billion), and the total investment in the first bridge project is approximately EUR 285 million (approximately RMB 2.34 billion).

The project is located at the North Elbe River crossing of the A1 Motorway in Hamburg. The original bridge was completed in 1963 and has long endured high-intensity traffic loads, with relatively serious structural damage. Currently, up to 131,000 vehicles per day use this section, about a quarter of which are heavy trucks. To protect the existing bridge, the relevant authorities have imposed speed limits, following-distance requirements and a ban on truck overtaking.

The first replacement bridge to be built, facing Bremen, is a cable-stayed structure approximately 380 meters long, arranged immediately adjacent to the existing bridge, with pedestrian and bicycle paths provided alongside. The first-phase design of the bridge includes 6 lanes, of which 4 are through lanes and 2 are weaving lanes, plus an emergency stopping lane.

During construction, the A1 Motorway will maintain 3 lanes in each direction. After the first bridge is completed, all traffic will be temporarily diverted to the new bridge, after which the existing North Elbe Bridge will be demolished and the second replacement bridge will be built. Once both new bridges are completed, the river crossing will have 4 through lanes in each direction, together with weaving lanes and emergency stopping lanes, and overall capacity is expected to double compared with the current situation.

The project adopts an early construction arrangement, under which some construction work that meets the conditions is carried out in advance while the planning approval procedure continues. Die Autobahn GmbH des Bundes and DEGES are advancing the project through an early implementation mechanism based on the degree of damage to the existing bridge and the urgency of the works, while the planning approval procedure will still proceed in parallel. The first replacement bridge is scheduled to be completed and opened to traffic in 2030, after which construction of the second bridge will begin.

The North Elbe Bridge is an important river crossing on Germany's A1 Motorway and a transport link connecting the Scandinavian Peninsula with the European continent. The route handles container collection and distribution for the Port of Hamburg, regional commuting and north-south freight transport in Europe, and some large and oversize vehicles also rely on the bridge to cross the Elbe. The bridge replacement project will dovetail with the plan to widen the A1 Motorway in the Hamburg area to eight lanes; the relevant road widening section lies between the Hamburg-Southeast motorway interchange and the Hamburg-Harburg exit.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com