Wedoany.com Report-Oct 10,Energy and marine consultancy company, ABL, has been appointed as marine warranty surveyor (MWS) to support the marine transportation and installation (T&I) operations for the Centre Manche 1 and Centre Manche 2 offshore substations in France.

Centre Manche 1 and Centre Manche 2 are part of two offshore wind projects – Appel d’Offre 4 (AO4) and Appel d’Offre 8 (AO8) – that aim to contribute towards the French government’s ambition of allocating 1 GW of offshore wind energy per year, from 2023 onwards.

Centre Manche 1 will connect the AO4 (1,050 MW) offshore wind farm and part of the AO8 (200 MW) to the 400 kV substation at Menuel through a 100-kilometre-long DC export cable.

Centre Manche 2 will connect the AO8 offshore wind farm to the 400 kV substation at Tourbe via a 105-kilometre-long DC cable. Both offshore substations will each have a capacity of 1.25 GW.

ABL’s operations in France will act as MWS for the transportation and installation campaign for the Centre Manche 1 and 2 offshore substations, the 100-kilometre-long DC export cable, and three 2-kilometre-long interstation links.

The company will handle the technical review and approval of all T&I engineering documents, participate in safety risk meetings (HAZID/HAZOP), assess the suitability of installation vessels, oversee onshore and offshore operations, and provide approval certificates.

Work is planned to begin in the third quarter of 2024 and is expected to continue until project delivery in 2032.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com