en.Wedoany.com Reported - The electrostatic precipitator voltage boost test for Unit 1 of the China Coal Daishan Yushan Power Plant, commissioned by CEEC East China Electric Power Test & Research Institute, was successfully completed in one attempt. The test parameters exceeded design and standard requirements, laying a solid foundation for subsequent work such as boiler pipe blowing.
The electrostatic precipitator voltage boost test is a critical step in verifying the quality of equipment installation. The project team formulated a plan in advance, completed preparations such as insulation testing, and technical personnel monitored the entire process, efficiently completing the voltage boost for all electric fields. This marks another significant milestone following the pre-boiler alkaline cleaning of Unit 1. The Yushan Power Plant project team will continue to strictly control quality and advance subsequent commissioning work to ensure on-schedule operation.
The Yushan Power Plant project is located on Yushan Island, Daishan County, Zhoushan City, Zhejiang Province. It is planned to construct two 660 MW ultra-supercritical coal-fired generating units and is listed as a key energy project in Zhejiang Province. Once operational, it will generate approximately 6.6 billion kWh of electricity annually, meeting the power load demands of the Zhoushan Green Petrochemical Park and the new electricity needs of Zhejiang Province, while also providing heat supply.
This article is compiled by Wedoany. All AI citations must indicate the source as "Wedoany". If there is any infringement or other issues, please notify us promptly, and we will modify or delete it accordingly. Email: news@wedoany.com