Ogden, US Advances 10.3 km Water Transmission Main Replacement Project

2026-11-16 14:47
Favorite

en.Wedoany.com Reported - On November 16, Ogden, Utah, US, announced the latest construction progress on the Canyon Water Transmission Pipeline Replacement Project. The construction team has completed the installation of 48-inch (approximately 1,219 mm) pipe into the trench in the dry lakebed area of Pineview Reservoir and is carrying out backfilling and compaction work. The project has a total investment of approximately USD 100 million and is planned to replace the full 6.4-mile (approximately 10.3 km) water transmission pipeline, connecting the city's water source well field near Pineview Reservoir with Ogden's 23rd Street water storage facility, serving more than 120,000 residents. The overall project is expected to be completed in spring 2029.

The project involves the renewal of an aging water transmission system that has been in operation for nearly 100 years. The existing main pipeline loses approximately 1 million US gallons (approximately 3,785 cubic meters) of treated drinking water per day due to leaks. Upon completion of the new pipeline, the corresponding water loss is expected to be reduced daily, improving the operational reliability of the city's primary water transmission corridor. Sunrise Engineering is responsible for engineering design, and Whitaker Construction is undertaking construction.

The Pineview Reservoir crossing section is a key focus of this round of construction. Because the pipeline needs to pass through the reservoir lakebed, the construction team first lowered the reservoir water level to a target elevation of 4,835 feet, then built a temporary construction road to complete dewatering, geological preparation, and material transport. Starting September 14, 2026, the construction team began implementing the reservoir crossing works and organized the transport and lifting of large-diameter pipe materials on the temporary construction access road. The 48-inch pipeline has now entered the trench, and construction personnel are carrying out backfilling, compaction, and subsequent pipe connection work.

The project adopts a combination of open-cut construction and slip-lining methods. In areas where excavation is possible, the construction team excavates trenches along the existing pipeline corridor, lays new pipe, and backfills; in sections constrained by terrain and existing facilities, slip-lining technology is used to rehabilitate the original pipeline. During the reservoir crossing construction, a 24-inch temporary bypass pipeline was also installed to support the operation of the water transmission system and pipeline connection work.

The project does not simply involve removing all old pipelines. Ogden plans to lay new pipeline alongside the existing water transmission corridor, and after the new system is put into operation, the original pipeline will be rehabilitated and retained as a backup water transmission line. Upon completion of the upgrade, the water transmission corridor will have two mutually independent transmission channels, enhancing the primary water transmission system's ability to cope with equipment failures and sudden pipeline damage. It should be noted that the 48-inch pipeline being installed in the reservoir crossing section is being implemented separately from the 36-inch pipeline installation arrangements in other sections of the project.

In addition to the reservoir crossing section, the pipeline replacement project in the eastern highlands area is also progressing and is scheduled for completion in December 2026. The upper Ogden Canyon pipeline renewal is scheduled for implementation from October 2026 to April 2027, and the subsequent works in the lower canyon Hermitage area are planned for construction from October 2027 to April 2028. Pipeline renewal in the Valhalla and Hermitage communities remains in the planning and design stage.

The project has a total investment of approximately USD 100 million, funded by the US Environmental Protection Agency's Water Infrastructure Finance and Innovation Act (WIFIA) program, the Drinking Water State Revolving Fund, and related funding under the US American Rescue Plan Act (ARPA). The Pineview Reservoir crossing project is scheduled for completion in early 2027.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com