Durham, USA Advances $6.5 Million West End Water and Sewer Pipeline Rehabilitation Project
en.Wedoany.com Reported - On November 14, the City of Durham, North Carolina, USA, announced the latest progress on Phase I of the West End water, wastewater, and stormwater pipeline rehabilitation project. The project is being constructed by J.F. Wilkerson Contracting Company, entered the construction phase in May 2026, and has a planned duration of approximately 8 months. It covers areas including Proctor Street, Arnette Avenue, Morehead Avenue, and Shepherd Street, and primarily involves the renewal of aging water mains, wastewater pipes, and stormwater drainage facilities.
The scope of work includes laying approximately 2,700 feet (823 meters) of 4–12 inch diameter ductile iron water mains, installing approximately 1,200 feet (366 meters) of 15–36 inch diameter stormwater pipes, and rehabilitating approximately 1,190 feet (363 meters) of existing 8-inch diameter wastewater pipes using the cured-in-place pipe (CIPP) method. The project also includes replacing residential domestic water and fire service connections, and upgrading manholes, valves, and related connection facilities. The contract also covers approximately 1,210 feet (369 meters) of water main renewal on Main Street and Broad Street.
The contract amount is approximately $5,938,300, with an additional contingency of $593,800, bringing the maximum contract amount to approximately $6,532,100. Construction is organized by block and by pipeline type, with separate crews advancing water, wastewater, and stormwater work simultaneously to reduce repeated excavation.
From November 16 to 20, construction crews will continue connecting new water service laterals on Arnette Avenue and installing stormwater pipes on Proctor Street; tree clearing will also be carried out near the intersection of Morehead Avenue and Shepherd Street to prepare for subsequent drainage pipeline construction. From November 23 to 25, stormwater pipe construction will extend to Morehead Avenue and Arnette Avenue. Segmented traffic control will be implemented during construction, and access to residences along the route will be maintained.
Related Products


ERW Welded Pipe (Black Pipe and Hot-dip Galvanized Steel Pipe)
Handan Zhengda Steel Pipe Co., Ltd.


CITIC Heavy Industries Tunneling Equipment Tunnel Engineering Shield Machine
CITIC Heavy Industries Co., Ltd.




145kV Porcelain Column Type Sulfur Hexafluoride Circuit Breaker
TBEA ZONFA Shanghai High Voltage Switchgear Co., Ltd.
YZR (450-560) Series Wound Rotor Three-Phase Asynchronous Motors for Crane and Metallurgical Applications
Jiamusi Electric Machine Co., Ltd.
Acoustic Mineral Fiber Ceiling Tile 595x595x12mm
Shanxi Pano Trading Co., Ltd