Ampeak UK Completes Installation of 55 Battery Units at 240 MWh Energy Storage Station

2026-11-16 15:39
Favorite

en.Wedoany.com Reported - On November 11, the 240 MWh energy storage project at the Uskmouth Sustainable Energy Park in Newport, Wales, UK, completed the delivery and installation of all 55 battery units and major electrical equipment, entering the preparation stage for first energization. The project is being developed by Ampeak Energy, with the battery system supplied by e-STORAGE, the energy storage subsidiary of Canadian Solar, and on-site installation carried out by Jones Bros Civil Engineering UK. The project is scheduled for first energization in November, with commercial operation planned for the first quarter of 2027.

The equipment installed includes 55 battery units, 36 inverters, 18 dual skid-mounted units and one main grid transformer. Major equipment was delivered within 22 days, with a 10-person team assembled by Jones Bros coordinating transport and installation sequencing; the total weight of equipment on site is close to 3,000 tonnes. e-STORAGE will also be responsible for subsequent commissioning of the energy storage system.

Concrete foundations for the battery and power conversion systems, cable trenches and prefabricated inverter cable trays have been completed on site, and the new on-site substation and high-voltage cables connecting to the national grid have also been installed. The project utilizes approximately two-thirds of the existing transmission cables from the former coal-fired power station, reducing the scope of new transmission infrastructure works.

During construction, the project team transported bulk aggregates by rail and crushed concrete from the demolition of existing facilities for reuse in on-site works. The park has also completed construction of a stormwater retention pond, along with associated fencing and landscaping works.

The next phase of the project will involve first grid energization, followed by battery system charge-discharge commissioning and joint testing of the power conversion system. Ampeak also plans to expand the existing energy storage project capacity from 240 MWh to 480 MWh; some equipment foundations required for the expansion have already been poured in advance, reserving space for subsequent battery installation. The expansion project is planned to proceed to financial close after the first-phase energy storage facility enters commercial operation.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com