Brighton & Hove City Council Approves £13.5 Million Procurement for Phase 3 of Coastal Defence Project
en.Wedoany.com Reported - On 12 January, Brighton & Hove City Council approved the launch of an open procurement for the construction of Phase 3 of the Brighton Marina to River Adur Coastal Flood and Erosion Risk Management Scheme, with an estimated contract value of approximately £13.5 million. The works are primarily located in Shoreham Harbour and the Adur-Worthing district, led by Brighton & Hove City Council in partnership with Adur & Worthing Councils, Shoreham Port Authority, and the Environment Agency. This procurement represents the final major construction phase of the overall coastal defence scheme, focusing on the repair and reinforcement of existing sea walls, the construction of new rock armour revetments, upgrades to coastal defence infrastructure, and the restoration of public access routes.
Phase 3 will centre on Shoreham Harbour and the surrounding coastal area. The works include repairing and strengthening existing sea wall structures, constructing new rock armour revetments in designated areas, and improving related coastal defence infrastructure. Upon completion, the facilities will provide flood and coastal erosion protection for port operational facilities, coastal transport links, utility infrastructure, employment land, and surrounding communities.
The project is the final major construction phase of the Brighton Marina to River Adur Coastal Defence Scheme. Phase 1 is substantially complete, covering the project business case, environmental assessment, planning approval, engineering design, and early works at Basin Road and the Lagoon area. Phase 2 is being implemented within the Brighton & Hove City Council area, including coastal defence improvements at Kings Esplanade and Southwick Beach, with completion expected in 2026. Phase 3 extends the defence works to Shoreham Harbour and the Adur-Worthing area, completing the main construction content of the overall scheme.
According to the council's latest funding plan, the total project investment is estimated at £36.5 million, comprising £25.9 million in flood defence grant funding from the Environment Agency and the Department for Environment, Food & Rural Affairs, £6.1 million from external partners, and £4.5 million from Brighton & Hove City Council. The council had previously approved a capital contribution of £11 million; with the increase in Environment Agency grant funding, the council's funding requirement has been reduced accordingly. The council also approved an increase of £9.8 million in the capital budget to cover the remaining funding requirement of the project.
Phase 3 will select a construction contractor through open tender, with an estimated contract value of approximately £13.5 million. Brighton & Hove City Council, as the lead authority, will be responsible for procurement and contract award. The works contract will take the form of the NEC4 Engineering and Construction Contract, and Shoreham Port Authority will bear the agreed costs of works related to its assets and land through a separate funding agreement.
Related Products


Pure Polyurethane Wall Panel BD-AEF-PIR-01
Baodu International Engineering Technology Co., Ltd.
Ceiling light | led Ceiling Light | LED Indoor light | LED Ceiling lighting
Queendom Group Technology Co., Ltd.

Metal sound barriers that can reduce the transmission of road noise
Hebei Jinbiao Construction Materials Tech Corp., Ltd.

ERW Welded Pipe (Black Pipe and Hot-dip Galvanized Steel Pipe)
Handan Zhengda Steel Pipe Co., Ltd.

High-toughness in-Situ Cold Recycling Technology for Original Structural Layers
Central Fortune Creation Technology Group Co., Ltd.

300mm Segment Type Countdown Traffic Light (Core Type)
Yangzhou FAMA Intelligent Equipment Co., Ltd.