UK HS2 Project Launches Installation of 1,516 Concrete Bridge Decks on Birmingham Viaducts
en.Wedoany.com Reported - On November 16, the UK High Speed 2 (HS2) Birmingham Curzon Street approach viaducts project completed the installation of a 125-tonne gantry crane. The construction team will use this equipment to carry out the lifting and installation of precast concrete bridge decks for five viaducts, with a planned total of 1,516 bridge decks to be installed over a construction period expected to last 18 months.

The gantry crane will first be deployed for construction on the Lawley Middleway Viaduct, then relocated to the Curzon 2, Curzon 1 and Duddeston Junction viaducts, completing bridge deck lifting in sequence according to the construction schedule. Once the equipment installation is complete, the site will enter a phase of continuous installation of precast bridge deck components.
The bridge decks are produced at a precast factory in Kingsbury, Warwickshire, UK. The factory previously manufactured 2,742 precast concrete segments for the HS2 Delta Junction viaducts and has now transitioned to producing bridge decks for the Curzon Street approach viaducts. The factory employs approximately 140 staff and supplies precast components to the Birmingham construction site.
The Curzon Street approach viaducts consist of five interconnected viaducts with a total length of over 1.5 km, connecting Birmingham city centre with Curzon Street Station. The route crosses existing railways and urban roads along the way, creating interfaces between bridge construction and surrounding transport infrastructure, which is why the factory-prefabrication and on-site lifting approach is adopted. The bridge decks are transported to the site in batches and then lifted and installed by the gantry crane.
The project is managed by HS2 Ltd, with Balfour Beatty VINCI responsible for the related civil engineering works. With the gantry crane now in operation, the project will continue to advance bridge deck installation across the five viaducts, followed by subsequent works on track structures and railway systems.
Related Products







145kV Porcelain Column Type Sulfur Hexafluoride Circuit Breaker
TBEA ZONFA Shanghai High Voltage Switchgear Co., Ltd.
CITIC Heavy Industries Tunneling Equipment Tunnel Engineering Shield Machine
CITIC Heavy Industries Co., Ltd.

YHTank8400N Solvent-Free Liquid Epoxy Coating
JIANGSU YUNHU NEW MATERIAL TECHNOLOGY CO., LTD.
Dual-curved Arm Rock Drilling Trolley RSD200D
Chengdu Ruilong Machinery Manufacturing Co., Ltd.