FERC Sets Environmental Review Schedule for 185,000 Dth/d Natural Gas Pipeline

2026-11-19 09:30
Favorite

en.Wedoany.com Reported - On November 18, the U.S. Federal Energy Regulatory Commission (FERC) published in the Federal Register the environmental review schedule for the North Extension natural gas pipeline project, planning to issue the environmental assessment report on March 26, 2027, and setting June 24 of the same year as the deadline for other relevant federal permitting agencies to render their decisions. The project is jointly applied for by Natural Gas Pipeline Company of America and Horizon Pipeline Company, and proposes to add 185,000 dekatherms per day of firm natural gas transportation capacity to Wisconsin; it remains in the federal approval stage.

The project plans to build a new CS 119 compressor station with 11,107 horsepower of installed capacity in Lake County, Illinois; add a 31,900-horsepower compressor unit at the existing CS 312 compressor station in Livingston County and modify the existing Unit 1 compressor unit. At the same time, an 11,107-horsepower compressor unit will be added at the existing CS 113 compressor station in Will County. The project will also construct approximately 11.5 miles (18.5 kilometers) of natural gas lateral pipeline between Lake County, Illinois and Kenosha County, Wisconsin, and build a new metering station and supporting facilities at the pipeline terminus.

The added natural gas transportation capacity will be used to meet the supply needs of Wisconsin Electric Power Company in southern Wisconsin. The project developer submitted its construction and operation permit application to FERC on August 12, under application number CP26-564-000. FERC issued a notice of acceptance of the application on August 19, and on September 22 initiated the environmental issue scoping and public comment process, requiring relevant agencies and the public to submit comments by October 22.

FERC received one comment during the environmental review process, concerning protection measures for birds, bats, and sensitive and rare habitats, as well as the cumulative environmental impacts arising from surrounding land use. The relevant issues will be incorporated into the environmental assessment report. According to the schedule announced on November 18, a 30-day public comment period will open after the environmental assessment document is issued, and other relevant agencies participating in the project approval must complete their federal authorization decisions within the specified deadline.

The previously submitted project application shows that construction and temporary construction land is expected to involve approximately 331.4 acres, and approximately 82 acres will be permanently occupied after the project is completed. About 90% of the proposed pipeline route will be laid along existing utility corridors. The project plans to add valve facilities and upgrade certain existing valve stations in Illinois, with the scope of work covering pipelines, compressor stations, metering systems, and ancillary facilities.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com