Germany's ANDRITZ completes delivery of 80-ton pumped storage pump-turbine

2026-11-19 11:28
Favorite

en.Wedoany.com Reported - On November 17, ANDRITZ's hydropower equipment manufacturing base in Ravensburg, Germany completed the delivery of a pump-turbine weighing approximately 80 tons and about 5.5 meters wide. The equipment has arrived at the underground powerhouse of the Forbach pumped storage power station in Baden-Württemberg, Germany. The equipment is intended for the modernization and expansion project of the Rudolf-Fettweis hydropower station. After pre-assembly at the Ravensburg factory, it was transported into the interior of the mountain by heavy-duty transport vehicles, creating conditions for subsequent unit installation.

The transport required passing through the narrow access tunnel of the newly built underground powerhouse. The narrowest point of the tunnel is only 5.8 meters wide, leaving a margin of approximately 0.3 meters compared with the maximum width of the equipment. The project team used heavy-duty transport vehicles to move the pre-assembled pump-turbine along the tunnel to the underground powerhouse, completing the delivery operation of large electromechanical equipment.

The Forbach expansion project is being advanced by German energy company EnBW and involves the modernization of the existing Rudolf-Fettweis hydropower station and the construction of new pumped storage facilities. Approximately 6 kilometers of tunnels have been excavated in the mountain, and the new underground powerhouse is 125 meters long and 40 meters high. According to the project plan, the total installed capacity of the power station will increase from 65 megawatts to 77 megawatts.

ANDRITZ is responsible for supplying the pump-turbines, motor-generators and auxiliary equipment for the project, and is also providing three Francis Compact turbines. With the core equipment delivered to the underground powerhouse, the project will enter the subsequent electromechanical installation phase and is scheduled to be connected to the grid in autumn 2027.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com