Maryland Launches Removal of Above-Water Structures of Key Bridge and Preparations for New Bridge Foundation Construction

2026-11-22 14:04
Favorite

en.Wedoany.com Reported - On November 19, the Maryland Transportation Authority (MDTA) Board approved the award of a contract for the removal of remaining structures of the Francis Scott Key Bridge and above-water ancillary works to Joseph B. Fay Company in the amount of USD 38,618,200 (approximately RMB 258 million). The project is located in the Patapsco River navigation channel in Baltimore and mainly includes removing the remaining steel girders and concrete piers of the original bridge, clearing underwater foundations and steel pipe piles, and providing working conditions for the foundation construction of the main span of the new bridge.

The contract number is KB-4906-0000, procured through competitive sealed bidding. According to the MDTA Board procurement documents, Joseph B. Fay Company's bid was USD 38,618,200, lower than the other two bidders, Seaward Marine Corporation at USD 63,569,000 and the McLean-United FSK joint venture at USD 67,862,500, and approximately 58% lower than the owner's engineering estimate of USD 91,941,000. The project is fully reimbursed with federal funds.

The demolition work first involves two groups of three-span steel plate girder structures over the Patapsco River. The contractor is required to remove and recover these steel girders and transport them to a storage location near the project. Concrete structure demolition includes the complete removal of 11 concrete piers and partial demolition of another 2 above-water concrete piers. The project also requires the removal of soil from inside 90 steel pipe piles located on both sides of the federal navigation channel to provide conditions for subsequent concrete pouring for the main span foundation of the new bridge. Each steel pipe pile has a diameter of 96 inches, approximately 2.44 meters.

According to the project description issued by MDTA during the same period, the above-water construction also involves the removal of 8 above-water piers of the original bridge, the removal of remaining land-based piers on both sides, and the demolition of 9 underwater foundations down to the riverbed mudline.

This contract follows the land-based demolition of the old bridge that was completed in February 2026. At that time, the construction team mechanically demolished the land-based structures of the original bridge and removed more than 20,000 tonnes of concrete bridge deck panels, pier components, and steel girders on the north and south sides. The new contract extends the scope of work into the waters of the Patapsco River to address the bridge structures and underwater foundations still remaining in the waterway.

Construction of the new bridge is already underway in parallel. MDTA disclosed that the construction team is installing permanent foundation piles and pier protection piles, and that the temporary above-water trestle for large construction equipment and material transport has also been completed. This demolition and above-water ancillary works will clear the remaining structures of the original bridge and create conditions for the foundation construction of the main span of the new bridge. Since the relevant steel pipe piles will become part of the main span foundation of the new bridge, the soil removal from within the piles and preparations for subsequent concrete construction need to be coordinated with the main works.

In May 2026, MDTA announced four separate procurement packages for the remaining reconstruction works, namely the remaining old bridge demolition and above-water ancillary works, the south land-based approach bridge, the north land-based approach bridge, and the main span and above-water approach bridge works. The packaged procurement approach was adopted to broaden contractor competition, increase opportunities for local enterprise participation, and enable different construction areas to proceed in parallel.

According to the Board procurement documents, the contract is expected to receive a notice to proceed in December 2026, with a contract duration of 671 calendar days. MDTA currently still aims to open the new Key Bridge to traffic by 2030.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com