STRABAG Group of Austria Launches Approximately 65 km Expansion of Poland's A2 Motorway

2026-11-23 16:02
Favorite

en.Wedoany.com Reported - On November 19, Austria's STRABAG Group announced the official launch of simultaneous expansion works on three contract sections of Poland's A2 motorway between Warsaw and Łódź, with a total construction length of approximately 65 km and a total contract value of approximately EUR 158 million (approximately RMB 1.161 billion). The project will expand the existing dual-carriageway four-lane motorway to six to eight lanes, along with pavement rehabilitation, repair of bridges and other structures, upgrading of traffic management facilities, and the use of recycled asphalt. The project owner is Poland's General Directorate for National Roads and Motorways (GDDKiA).

The works comprise three contract sections: B, C, and D. Section D has a total length of 17.2 km, located between Konotopa and Grodzisk Mazowiecki; Section B has a total length of 21.8 km, connecting Ryszkiwice with the border between Łódź Voivodeship and Masovian Voivodeship; Section C has a total length of 25.5 km, extending to the Grodzisk Mazowiecki interchange area. The three sections total approximately 64.5 km, consistent with the approximately 65 km total construction length announced by the Group.

The expansion works will adjust lane configurations according to traffic demand. Most sections will be increased from the existing two lanes per direction to three lanes, and some sections near Warsaw will be increased to four lanes per direction. In addition to the new lanes, the works also include comprehensive rehabilitation of existing pavement, repair of bridges and other engineering structures, replacement of safety barriers and noise barriers, and upgrading of traffic management systems and road lighting facilities.

The works will be carried out while maintaining normal motorway traffic. During construction, at least two lanes will remain open in each direction of travel to minimize the impact on the Warsaw–Łódź transport corridor. According to the schedule announced by STRABAG Group, Sections B and D are planned for completion by the end of 2027, and Section C is expected to be completed in early 2028.

The use of recycled asphalt is a key technical element of this project. During construction, old asphalt mixture from the demolition of existing pavement will be processed through recycling and reused in the production of new asphalt mixture. The project requires a recycled asphalt material content of 35% in the asphalt binder course and base course, and 20% in the surface course. To meet the demand for large-scale processing of recycled materials, STRABAG Group has retrofitted equipment at three asphalt mixing plants to enable them to process more reclaimed asphalt using hot recycling technology, combined with foamed bitumen technology to improve the production process of recycled mixtures.

The hot recycling process involves heating reclaimed asphalt materials so that they can re-enter asphalt mixture production, reducing the use of new bitumen and virgin aggregates. Foamed bitumen technology involves adding a small amount of water to hot bitumen, causing the bitumen to expand rapidly and form a foamed state within a short time, improving its coating and mixing conditions with mineral aggregates. The combined application of these two technologies can increase the recycling rate of old pavement materials and reduce raw material consumption and construction energy consumption.

Road-supporting energy systems are also included in the upgrade scope. The project plans to deploy photovoltaic systems, energy storage equipment, wind power generation facilities, and high-efficiency LED lighting. According to arrangements published by the project owner, the upgraded motorway lighting, weather monitoring stations, and other operational facilities will be powered by renewable energy.

The A2 motorway is a major transport artery connecting eastern and western Poland, and the Warsaw–Łódź section serves the transport link between the capital and the industrial, logistics, and commercial areas of central Poland. The three contract sections undertaken by STRABAG Group are part of the expansion plan for more than 90 km of this route, with another section being implemented by a different contractor. Upon completion of all works, the road capacity of this corridor will be increased, improving traffic connections between the Warsaw metropolitan area and surrounding logistics nodes.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com