RWE Receives First Monopiles for 900 MW Offshore Wind Project in Germany

2026-11-24 10:35
Favorite

en.Wedoany.com Reported - On November 23, German energy company RWE announced progress on equipment deliveries for the Nordseecluster B offshore wind project. The first batch of 10 monopile foundations has arrived at the Port of Eemshaven in the Netherlands and been unloaded. The project has an installed capacity of 900 MW, and the monopile foundations are manufactured and supplied by China's Dajin Heavy Industry.

The monopile foundations have an average length of approximately 81 meters and a unit weight of approximately 1,350 tons. From 2026 to 2027, the 60 monopile foundations required for the project will be transferred successively through Buss Ports' heavy-lift terminal at the Port of Eemshaven.

The Nordseecluster offshore wind cluster is located approximately 50 kilometers north of the island of Juist in the German North Sea and is being built in two phases. The 660 MW first-phase wind project is scheduled to be fully operational in early 2027. The second phase is planned to begin foundation installation in 2027, with the installation of 60 wind turbines carried out in 2028, and commercial operation starting in early 2029.

Once both phases are fully completed, the project is expected to generate approximately 6.5 billion kWh of electricity annually. RWE and Norges Bank Investment Management hold 51% and 49% stakes in the project, respectively, with RWE responsible for construction and subsequent operations.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com