Australia's Latrobe Magnesium Completes Equipment Installation at Magnesium Metal Demonstration Plant

2026-11-24 13:36
Favorite

en.Wedoany.com Reported - On November 23, Australia's Latrobe Magnesium announced that all equipment installation has been completed for the Stage 1B pyrometallurgical project at its magnesium metal demonstration plant in the Latrobe Valley, Victoria, with overall commissioning progress reaching 78%, up from 50% at the end of October. The briquetting production line, reduction furnace, and charging system have all been installed in place, and the reduction furnace has begun phased heating. The company plans to produce its first batch of magnesium metal products with a magnesium content exceeding 98% by the end of 2026.

This round of installation work covered briquetting production equipment, the reduction furnace, and the associated charging system. The reduction furnace has completed ignition testing, and the final furnace body seal installation has been completed. Trial material commissioning of the briquetting production line has also been completed, with the reagent handling, grinding, and briquetting equipment having completed the corresponding tests. The first batch of magnesium oxide raw material briquettes has been produced and is ready to be fed into the reduction furnace for subsequent testing.

In terms of reduction system commissioning, the project has initiated phased heating of the furnace body, with final charging system testing being conducted simultaneously. Once the reduction furnace reaches the specified operating conditions, the project will carry out commissioning of feeding into the reduction retorts and enter the testing phase of the metal extraction system. Verification of the magnesium metal production process still requires completion of the above commissioning procedures and has not yet entered the formal magnesium metal production stage.

Operational preparation work for the project is progressing in parallel, with key positions fully staffed and related training already underway. All reagents for the subsequent 4-week trial run have arrived on site. The company plans to confirm actual project completion after completing feed commissioning and hand over the facility to the operations team for the first batch of magnesium metal production.

Regarding project costs, the Stage 1B pyrometallurgical works remain within the original budget of AUD 6.1 million, and the remaining construction and commissioning expenditures are expected to be consistent with the fund utilization plan under the previous equity financing arrangement. The company also records that no recordable safety incidents have occurred since the project's inception.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com