Claremont, USA Plans $2.788 Million Stormwater Network Upgrade

2026-11-25 17:29
Favorite

en.Wedoany.com Reported - On November 24, the Claremont City Council in California, USA, placed the Colby Circle Storm Drainage Improvement Project on its agenda for review, proposing to award a $2,402,800 construction contract to All Cities Engineering Inc. and to engage TKE Engineering Inc. for construction inspection and project management at a contract amount not to exceed $145,300. The total project budget is approximately $2,788,300 (about RMB 19.79 million), primarily to build storm drainage networks and underground infiltration facilities along Colby Circle and Oxford Avenue, in order to alleviate road ponding and localized flooding during heavy rainfall.

The project number is CIP 2026-04. The scope of work includes new storm drain mains, branch pipes connecting to catch basins along the route, and drywells installed upstream of some catch basins. The drywells collect and infiltrate stormwater, reducing surface runoff before it enters the storm drain network and lowering the load on the drainage system during heavy storms.

The project adopts a high-density polypropylene pipe (HP Pipe) solution. The bidding included both reinforced concrete pipe (RCP) and high-density polypropylene pipe options, and a total of 10 firms submitted bids by September 30, 2026. All Cities Engineering Inc. became the lowest responsive and responsible bidder with a high-density polypropylene pipe bid of $2,402,775, lower than its reinforced concrete pipe bid of $2,449,075.

Road restoration is also part of the construction scope. After the storm drain mains and branch pipes connecting to catch basins are laid, the contractor will perform 2-inch depth milling and standard hot-mix asphalt paving on the affected sections of Colby Circle and Oxford Avenue, and re-stripe the road markings. The new drainage system will also connect to the storm drain network of the Foothill Boulevard Master Plan Improvement Project completed in 2020.

The construction contract bid is $2,402,775. City staff recommend establishing an additional 10% construction contingency of $240,278, for a total construction contract authorization limit of $2,643,053. TKE Engineering Inc. will be responsible for construction inspection and construction management, with service fees not to exceed $145,278. The total project cost is $2,788,330.

Project funding comes from the Measure W Fund and the Drainage Fund. Of this, the Measure W Fund covers $2,059,330 in construction costs, and the Drainage Fund covers $343,445 in construction costs and also covers the construction contingency, construction management, and inspection costs.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com