First Tunnel on the Hangzhou Section of the Hangzhou-Chun'an-Kaiping Expressway of Zhejiang Communications Group Achieves Breakthrough

2026-11-25 17:31
Favorite

en.Wedoany.com Reported - On November 23, the left tube of Wujinshan No. 2 Tunnel on Section TJ07 of the Hangzhou section of the Hangzhou-Chun'an-Kaiping Expressway, constructed by Zhejiang Communications Group, was successfully holed through, making it the first tunnel on the entire Hangzhou section of the expressway to achieve breakthrough. The left tube of the tunnel has a bore length of 305 meters and an open-cut section of 10 meters, and was completed in approximately 7 months, marking the transition of the project's tunnel works from portal excavation to main structure formation.

Wujinshan No. 2 Tunnel is located in Tonglu County, Hangzhou. The tunnel has relatively shallow cover, and the surrounding rock is highly weathered, posing risks of roof collapse and rockfall. Its exit is only 50 meters from the entrance of the Wujinshan Extra-Long Tunnel, resulting in cross-construction at multiple portals. The site is also subject to ecological and environmental protection requirements for the hilly terrain of western Zhejiang, making construction organization and safety control relatively difficult.

This section is a pilot for the third batch of full-process mechanized tunnel construction in Zhejiang Province. The construction team has been equipped with complete sets of machinery, including three-boom rock drilling jumbos and intelligent arch trolleys, to reduce manual operations at the tunnel face and lower the exposure of personnel to high-risk operations. The project implements 24-hour cyclic construction, with technical personnel on rotating shifts to promptly conduct on-site assessment and handling of abnormal conditions such as rockfall and damage to steel arches.

In response to the shallow cover and weathered surrounding rock conditions, the construction team used ground-penetrating radar for advanced geological forecasting and dynamically adjusted support parameters according to geological changes. In terms of construction quality control, the project applied an invert 3D scanning automatic measurement system, a robotic steel arch production line, and 3D laser scanning technology to carry out digital measurement and quality control of concealed works and key construction processes.

Following the breakthrough of Wujinshan No. 2 Tunnel, Section TJ07 will continue with the construction of Wujinshan No. 1 Tunnel and the Wujinshan Extra-Long Tunnel. The Wujinshan Extra-Long Tunnel, with a left tube length of 3,890 meters and a right tube length of 3,866 meters, is a key controlling project on the Hangzhou section of the Hangzhou-Chun'an-Kaiping Expressway and is scheduled for completion in August 2028.

The Hangzhou section of the Hangzhou-Chun'an-Kaiping Expressway is an important component of the G2531 Hangzhou-Shangrao Expressway, with a total route length of 184.4 kilometers. Upon completion, the project will improve the expressway network in western Hangzhou and enhance traffic conditions in areas along the route, including Tonglu and Chun'an.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com