Indian Cabinet Approves Construction of 2 Million TEU Second Container Terminal at Kamarajar Port

2026-11-26 15:51
Favorite

en.Wedoany.com Reported - On November 25, the Cabinet Committee on Economic Affairs of India approved the construction of a second container terminal at Kamarajar Port in Tamil Nadu, with an estimated project investment of INR 428.826 billion (approximately RMB 3.1 billion). The new terminal is designed with an annual throughput capacity of 2 million TEU, a planned 900-meter quay line, and a design draft of 18 meters, capable of accommodating ultra-large container vessels with a capacity of 24,346 TEU and a length of 400 meters.

The project is located in the Chennai–Ennore Industrial Economic Zone on India's east coast, covering an area of approximately 111 acres (about 45 hectares). It will be implemented through a public-private partnership model via the Design, Build, Finance, Operate, and Transfer (DBFOT) approach, with a concession period of 40 years. The concessionaire will be selected through international open bidding, and the winning enterprise will be responsible for financing the terminal construction and recovering the investment through subsequent operational charges.

The terminal will be built in two phases. Phase I involves an investment of INR 242.932 billion for the construction of a 500-meter quay line with a designed annual throughput capacity of 1.1 million TEU; Phase II involves an investment of INR 185.894 billion to add a 400-meter quay line and 900,000 TEU of annual throughput capacity. According to the schedule announced by the Indian government, Phase I is planned to be completed within 24 months after the concession is awarded, with commercial operations commencing in the 25th month; Phase II will be constructed from the 25th to the 48th month, and the entire terminal is planned to enter full commercial operation in the 49th month.

The investment in the main terminal works will be borne by the winning concessionaire. In addition, Kamarajar Port Limited will separately invest INR 45 billion (approximately RMB 325 million) for dredging works. The two investments total approximately INR 473.826 billion (approximately RMB 3.42 billion). The dredging costs are not included in the INR 428.826 billion public-private partnership project investment.

The new terminal will feature a 900-meter-long quay line, 30-meter-wide berths, a berth front water depth of 20 meters, and a design draft of 18 meters, capable of meeting the berthing requirements of large container vessels with a capacity of 24,346 TEU and a length of 400 meters. The deep-water berths and adaptability to large vessels are the main engineering features of this project. Upon completion, it will enhance Kamarajar Port's ability to accommodate ocean-going mainline container vessels and reduce the need for some cargo to be transshipped through overseas deep-water transshipment hubs.

The new terminal will primarily serve import and export cargo from the Chennai–Ennore Industrial Economic Zone and the southern Indian hinterland, with a focus on automobiles and parts, engineering machinery, electronic products, chemical products, and other manufactured goods. Port authorities expect that the additional 2 million TEU annual handling capacity will increase opportunities for direct calls by large container vessels and reduce dependence on overseas transshipment hubs and feeder services.

According to the project expectations announced by the Indian government, the construction phase will create approximately 750 jobs, and approximately 800 additional jobs are expected after operations commence.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com