UK’s First Co-located Solar and Storage Facility Connects to Transmission Network
2024-11-14 11:13
Favorite

Wedoany.com Report-Nov 14, Developer and independent power producer (IPP) Cero Generation has connected its Larks Green solar and storage facility to the UK transmission network.

The 70MWp solar PV part of the project was completed in April 2023, becoming the first standalone solar PV plant to connect to the transmission network. Energisation of the 49.5MW/99MWh battery energy storage system (BESS) co-located with the solar development, makes the facility the first of its kind to be transmission connected in the UK.

The project has a 120MW grid connection, which, as commercial manager Patrick O’Connor told Energy-Storage.news, means “the BESS is not competing with the solar for export capacity”.

Marta Martinez Queimadelos, CEO of Cero Generation, who said she was “delighted” to have reached this milestone, explained: “This co-located solar and battery storage project will allow power to be delivered to the grid when it is needed, coupling demand and generation. The development of these projects will help to reduce the cost of energy for households, while also reducing the UK’s reliance on fossil fuels.”

Rabobank financed both the BESS and the solar PV elements. Cero generation and its UK development partner Enso Energy said that working on the project has established long-term partnerships with both Canadian Solar, as the lead on the engineering, procurement and construction (EPC) for the battery, and EDF, as the battery performance optimiser.

To connect the solar PV facility to the transmission network, Cero and Enso, in collaboration with National Grid, installed new switchgear at the site. A high-voltage cable also connected the solar farm to the Iron Acton substation near Bristol.

The partnership between Enso and Cero was originally signed between Enso and Macquarie’s Green Investment Group (GIG), before GIG launched Cero and consolidated its existing and future European solar activities, including the UK pipeline, into the new developer.

On 11 November, Solar Power Portal reported that National Grid had completed upgrades to its Drax 132kV substation to accommodate the transmission connection of TagEnergy’s 100MW/200MWh BESS.

According to the renewable energy developer, the facility in North Yorkshire is the largest transmission-connected battery storage system in the UK.

A connection to the higher voltage transmission system, rather than a local distribution network, means that the energy generated at a site, or discharged from a battery, can be transported across greater distances.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com
Lastest Bulletin
1
Inyanga Marine Energy Group welcomes the Welsh Government’s Renewable Energy Sector Deal.
2
2026 China's Local Blueprint: Shanghai, Sichuan, Hubei, Anhui, and Other Regions Include Fusion Energy Projects in Their 2026 Key Project Lists
3
China Nuclear Environmental Protection: Concentrating Efforts on Reform for Breakthrough, Striving to Create a New Situation in the Nuclear Environmental Protection Industry
4
Fu Liangqian Appointed as Vice President of the Southwestern Institute of Physics (SWIP) under China National Nuclear Corporation
5
China Nuclear Power Equipment Holds Kick-off Meeting for the Promotion and Implementation of the "1455" Project
6
Zhu Xiaoyan, Member of the Party Leadership Group and Deputy Director of the East China Energy Regulatory Bureau: Seizing Opportunities, Striving Diligently to Contribute East China Energy Regulatory Strength to Building a Strong Energy Nation
7
CGNPC Environmental Protection Party Committee Deputy Secretary and General Manager Ren Junhua Meets with Southwest University of Science and Technology Vice President Fa Tao and Delegation
8
China National Nuclear Power 5th Construction Company Selected as a National Intellectual Property Demonstration Enterprise
9
2026 China-Korea Nuclear Energy Industry Exchange Seminar Concludes Successfully in Qingdao — Focusing on Supply Chain Collaboration and Overseas Expansion, Discussing New Opportunities for China-Korea Nuclear Energy Cooperation
10
China's First Domestically Developed "Hualong One" Main Steam Release Isolation Valve Successfully Shipped to Guangdong Lufeng Nuclear Power Plant