en.Wedoany.com Reported - The Ruihua Commercial Building project, undertaken by Gansu Construction Investment Group's First Construction Company, has successfully completed the mass concrete pouring operation for the main building's raft foundation, achieving a key milestone on schedule. The foundation construction of the project's main building has been successfully concluded, officially entering the new phase of main structure construction.

Concrete pouring of raft foundation for the main building of Ruihua Commercial Building project in Gansu, China completed

The project is located in Gansu Province, China. The main building's foundation raft, serving as the core load-bearing structure, utilized mass concrete construction with a total pouring volume of 1,500 cubic meters. The pouring operation faced numerous challenges due to factors such as limited site space, large pouring volume, high temperature control standards, and significant difficulties in construction organization and traffic coordination.

To ensure the pouring task was completed safely, with high quality and efficiency, the project department, in collaboration with the First Construction Casting Company, planned ahead and made meticulous arrangements. They scientifically prepared a specialized plan, precisely coordinated the entire process of concrete production, transportation, and pouring, reasonably determined the batching start time, transportation routes, and pouring sequence, and conducted specialized technical and safety briefings to fully ensure the efficient connection of technology, materials, personnel, and machinery.

During the pouring period, the project department strictly implemented mass concrete construction specifications, fully carried out key techniques such as inclined layered pouring, secondary vibration, and film-covered curing. Dedicated personnel were assigned to 24-hour rotating shifts for real-time temperature monitoring, precisely preventing the risk of hydration heat cracks, and strictly adhering to safety bottom lines and quality standards. After continuous day-and-night efforts, the pouring task was completed smoothly and orderly.

The Ruihua Commercial Building project is constructed by Gansu Construction Investment Group's First Construction Company. The successful completion of this mass concrete pouring for the main building's raft foundation has laid a load-bearing foundation for the subsequent main structure construction. During construction, the project team adopted measures such as layered pouring and real-time monitoring to address the challenges of narrow site space and temperature control.