Kyushu Electric to Replace Steam Turbines at Genkai Nuclear Plant
Wedoany.com Report-Jan 10, Kyushu Electric Power Co. has announced that the steam turbines at its Genkai-3 and -4 Nuclear Power Plants will be replaced, pending the approval of new design and work plans by authorities.
According to the Japan Atomic Industrial Forum, the company has submitted applications to the Nuclear Regulation Authority and is waiting for approval.
The upgrades at Unit 3 will run from April 2027 to March 2028 and at Unit 4 from April 2028 to March 2029. Kyushu Electric said that the replacements would “improve reliability and generation efficiency.”
Kyushu Electric tapped Mitsubishi Heavy Industries for the project. The steam turbines to be delivered will include 54-inch blades that the company itself has designed and developed.
Related Products

CAP1400 main feedwater flow nozzle flowmeter.
Jiangsu Hongda Instrument Technology Co., Ltd.




Safe, efficient, intelligent energy storage, creating smart homes and making life more convenient# Home Energy Storage # Supercapacitors # Energy Storage # Wall Mounted # Safe Electricity Use
Gonghe Power Co.,LTD



Jin Haiyan® Nuclear Island Special Glass Wool (JHY-NW)
BBMG ENERGY SAVING MATERIAL & TECHNOLOGY (DACHANG)CO., LTD.

Centrifugal chiller for third generation nuclear power AP/CAP series
Chongqing General Industry (Group) Co., Ltd.