Gru’s Biomass Power Plant Will Remain Shut Down
2024-11-02 11:48
Favorite

Wedoany.com Report-Nov 2, GRU’s controversial biomass power generating plant will remain shut down due to mechanical damage.

The agenda for next week’s GRU Authority Board meeting says the damage to a “Blade wheel” in the turbine was found while the biomass plant was shut down for a ten year inspection.

The damage put “The plant at risk of catastrophic failure.”

The part was sent to the manufacturer for repairs, which are expected to take up to three months and cost more than a million dollars.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com