All Suction Bucket Foundations Stand at Greater Changhua 2B Offshore Taiwan
Wedoany.com Report-May 26, Ørsted has completed the installation of all 24 suction bucket jacket (SBJ) foundations for the 337.1 MW Greater Changhua 2b offshore wind farm, located 35-60 kilometers off Changhua County, Taiwan. The installations, carried out by Heerema Marine Contractors’ heavy-lift vessel Aegir, began in early April 2025 and finished ahead of schedule in just over a month.
The SBJ foundations utilize suction bucket technology, which eliminates the need for piling and securely anchors structures to the seabed. This innovative approach enhances efficiency and minimizes environmental impact during installation. The foundations were supplied by Petrovietnam Technical Services Corporation (PTSC) and HSG Sungdong, with marshalling and lifting activities managed by Mammoet-Giant Taiwan, a joint venture between Mammoet and Giant Heavy Machinery Service.
Construction of the 920 MW Greater Changhua 2b and 4 offshore wind farms began in February 2025. Ørsted announced progress on social media, stating: “Meanwhile, foundation installation at the Greater Changhua 4 Offshore Wind Farm is also progressing. We’ll continue to make the most of the favorable weather windows and push forward with full momentum.” The timely completion of the 2b foundations reflects Ørsted’s efficient project management and favorable weather conditions.
The Greater Changhua 2b and 4 wind farms will feature Siemens Gamesa 14-236 DD turbines, the largest of their kind in the Taiwan Strait, delivering significant clean energy capacity. These projects strengthen Taiwan’s renewable energy infrastructure, supporting the region’s transition to sustainable power sources and contributing to local economic growth through job creation and industry partnerships.
Ørsted’s commitment to advancing offshore wind energy in Taiwan is evident in the rapid progress of the Greater Changhua projects. The successful installation of the SBJ foundations at 2b marks a key milestone, positioning the wind farm to deliver reliable, renewable energy upon completion. The ongoing work at Greater Changhua 4 further demonstrates Ørsted’s dedication to expanding clean energy solutions in the region.
Related Products


G.652.D Wavelength-extended Non-dispersion Shifted Single-mode Optical Fiber
HONGAN GROUP CO., LTD.
GW4-40.5/72.5/126/145/170/252/363/420 Series Double-column Horizontal Rotary High-voltage AC Disconnect Switch
SHANDONG TAIKAI DISCONNECTORS CO., LTD.
IGBT Hydrogen Production Power Supply - High Power Air Cooling
Beijing Zhengzhuo Engineering Technology Co., Ltd.
72.5kV 1250A 31.5kA SF6 free Gas-insulated Metal-enclosed Switchgear
Zhejiang Juhonkia Intelligent Electric Co., Ltd.




YE3 Series Low Voltage High Power Three-Phase Asynchronous Motor
Shandong Lijiu Electrical Machinery Co., Ltd.

1000kV Jin Southeast-Nanyang-Jingmen UHV AC Transmission and Transformation Pilot Demonstration Project
Anhui Hongyuan Steel Tower Co., Ltd.