Carnegie of Australia Completes First-Stage Offshore Deployment of Wave Energy Device in Spain
en.Wedoany.com Reported - On November 16, Australia's Carnegie Clean Energy announced the results of the first-stage offshore deployment of its CETO wave energy device. On November 14, the device's buoyancy actuator was towed from the Port of Bilbao, Spain, to the Biscay Marine Energy Platform (BiMEP) off the coast of Armintza in the Basque Country, and was connected to a pre-installed dedicated anchoring and mooring system. This deployment is part of the first phase of the ACHIEVE demonstration project, and the device launch, towing, and offshore mooring operations have been completed.

The buoyancy actuator was machined in three sections by a local manufacturer in the Basque Country, then transported to the Port of Bilbao for quayside assembly. The project team used a crane to lift the assembled equipment into the water and completed port berthing, towing preparation, and offshore transport. On-site operations also included the installation of the anchoring system, coordination of work vessels, and offshore mooring connections.
This round of offshore deployment completed the relevant permitting procedures with port and maritime authorities for quayside assembly, heavy lifting, vessel departure, and offshore installation. The project team also inspected the equipment's performance during towing and under actual sea conditions, and verified the local supply chain, port logistics, and offshore installation processes. These operations correspond to the phased milestones set out in the ACHIEVE project and can trigger the disbursement of subsequent project funding.
Under the next steps, the buoyancy actuator will remain offshore for a short period and will be towed back to the Port of Bilbao depending on weather windows and vessel availability. During the European winter of 2026 to 2027, the power take-off module and electrical module will undergo final integration testing onshore, including mechanical, electrical, control, and communication functions.
Carnegie plans to carry out the second-stage offshore deployment in spring 2027, at which time the power take-off module and electrical module that have completed onshore testing will be integrated with the buoyancy actuator to form a complete CETO wave energy generation system, and grid-connected testing will be conducted at BiMEP.
Related Products




Perfluorinated Ionic Membrane-CM-10N Series Membrane
Guizhou Juneng Century Technology Co., Ltd

Yingping Mining Section Open-pit Tailings Backfill Treatment of Goaf Ecological Restoration EPC Project
China Bluestar Lehigh Engineering Corporation

6kV-35kV Medium and High Voltage Direct-Connected Energy Storage System
Hainan Jinpan Smart Technology Co., Ltd.
NISELA Series Environmentally Friendly Gas-Insulated Ring Main Unit
XJ DELISHIER ELECTRIC CO., LTD.
YE3 Series Low Voltage High Power Three-Phase Asynchronous Motor
Shandong Lijiu Electrical Machinery Co., Ltd.