Egypt's EDECS Group Wins Contract for Reinforcement of 610-Meter Quay at Port of Luanda, Angola

2026-11-17 14:50
Favorite

en.Wedoany.com Reported - On November 16, Egypt's EDECS Group announced that it had been awarded a design-build contract by UAE-based DP World for the reinforcement and upgrade of the quay at the container terminal of the Port of Luanda, Angola. The project covers the existing 610-meter quay wall and primarily involves providing the structural foundation and supporting facilities for the installation of rail-mounted ship-to-shore container cranes. The scope includes 120 foundation piles, reinforced concrete structural strengthening, crane rail systems, and the construction of power and fire protection facilities.

The focus of this project is to strengthen the existing quay structure so that it can support rail-mounted ship-to-shore cranes. Compared with the current practice of using mobile harbor cranes for ship loading and unloading, rail-mounted cranes can travel along rails on the quay to provide continuous loading and unloading services for container ships. Once the quay upgrade is completed, ship loading and unloading efficiency will improve, and the terminal's ability to accommodate larger, deeper-draft vessels will be enhanced.

The foundation works include the installation of 120 piles with a diameter of 1 meter and a maximum length of 45 meters, providing the load-bearing foundation for the new crane rails and quay structure. EDECS will also construct land-side reinforced concrete rear capping beams and extend the existing quay crown beam to accommodate the load requirements of the new equipment. Pile foundation construction will be accompanied by ultrasonic cross-hole testing, high-strain dynamic testing, pile integrity testing, and working and non-working load tests to verify the integrity and load-bearing performance of the foundation structure.

The crane supporting works include the installation of A150 crane rails, as well as buffer stops, securing pins, anchoring devices, cable reels, and guard band systems. These facilities are used for crane travel, parking, securing, and power supply, forming the infrastructure system for rail-mounted handling equipment. The project also includes quay power supply cables and conduits, substations, low-voltage and extra-low-voltage distribution facilities, and the construction of a fire protection pipeline network, providing support for subsequent crane installation and operation.

This contract is part of DP World's ongoing upgrade of the Luanda container terminal. In October 2026, DP World announced a USD 90 million port expansion plan to extend the total quay length from 610 meters to approximately 830 meters, adding about 222 meters of quay, while expanding the yard area from 27 hectares to 37 hectares. The equipment plan includes the addition of 3 ship-to-shore cranes and 12 semi-automated rubber-tyred gantry cranes.

Under the previously announced expansion plan, the annual design handling capacity of the Luanda container terminal will increase from 500,000 TEU to 1.2 million TEU, with the ability to serve two large post-Panamax container ships simultaneously. Since taking over the terminal in 2021, DP World has continued to invest in improving handling equipment, yards, and reefer facilities.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com