Design-Build Tender Launched for 123 km Western Section of Bordeaux–Toulouse High-Speed Rail
en.Wedoany.com Reported - On November 23, SNCF Réseau issued a design-build tender notice for the western section of the Bordeaux–Toulouse high-speed rail line, covering approximately 123 km and connecting Saint-Médard-d'Eyrans, south of Bordeaux, with Sainte-Colombe-en-Bruilhois in Lot-et-Garonne. The project adopts an integrated design-build model, with a deadline for applications to participate in the tender of January 5, 2027.
This tender is designated Corea Ouest. The scope of works includes earthworks and civil engineering for the roadbed, structures such as bridges, track laying, construction of catenary and traction power supply facilities, as well as connections to and modifications of the existing rail network. The contracting consortium will also need to build a construction base and associated rail connection lines at Saint-Selve, with some of the site to be subsequently converted into a maintenance base. Modifications to certain existing rail facilities south of Bordeaux are also included in the contract scope.
Signaling, communications and other rail systems are not within the scope of this main contract, but the contractor is required to reserve cable ducts, auxiliary power supply and other system interfaces. The related signaling and communications works will be procured separately to ensure technical interfacing with the line's civil engineering and track works.
A separate Corea Est contract covers the eastern section of the Bordeaux–Toulouse high-speed rail line, extending from Sainte-Colombe-en-Bruilhois to Saint-Jory north of Toulouse, and includes two new stations at Agen-Brax and Montauban-Bressols, as well as a construction base and two maintenance bases.
Both lots adopt the integrated design-build model, with a single consortium responsible for detailed design development and project implementation. The project development agency stated that this model combines engineering design with construction planning at an early stage, with the scope covering disciplines including earthworks, bridges, track and catenary. Signaling and communications systems are procured separately but must be coordinated at the design stage for interfaces.
The Bordeaux–Toulouse high-speed rail line is part of the French Ligne Nouvelle Sud-Ouest (LNSO) program. SNCF Réseau currently targets the end of 2032 as the commissioning date for the Bordeaux–Toulouse line, but the French infrastructure advisory committee has previously considered 2035 to be a more realistic commissioning date. With the launch of the western section tender, the project will enter the stage of selecting design-build contractors.
Related Products

3m intelligent buoy combining navigation safety and real-time marine monitoring integrated navigation and marine monitoring system for real-time maritime data
Chengdu Dixin Technology Co., Ltd.



China - Alashankou/Khorgos - Europe Full Range Transportation (Mala/Hamburg/Duisburg/Budapest, etc.)
Shenzhen Neptune Logistics Co., Ltd.
CLW5180TXSD6 Dongfeng Tianjin Washing and Sweeping Truck
ChengLi Special Automobile Co., Ltd.
GSR6-27.5kV SF6 Free Gas-insulated Metal-enclosed Switchgear
Zhejiang Juhonkia Intelligent Electric Co., Ltd.
XC-6000e Type Aviation Catering Truck (Fuel Type)
Shenzhen CIMC-TianDa Airport Support Ltd.