Boston North Station Railway Bridge Reconstruction in the U.S. Adopts Dual-Bridge Scheme, Expanding Cross-River Tracks to 6
en.Wedoany.com Reported - On November 24, a joint venture comprising Skanska and Koch implemented a new dual-bridge design for the Boston North Station No. 1 Railway Bridge replacement project, adjusting the original plan of building three new bridges and one temporary railway bridge to two three-track vertical lift bridges. According to Skanska, the optimized design is expected to save Massachusetts approximately USD 140 million (approximately RMB 990 million), while shortening the construction organization period and reducing project risks.

The project is located between Boston, Cambridge, and Somerville in Massachusetts, U.S., spanning the Charles River. It is implemented by the Massachusetts Bay Transportation Authority (MBTA), with the Skanska-Koch joint venture responsible for design and construction and VHB responsible for engineering design. The overall project scale is approximately USD 1.3 billion, and the design-build contract amount previously announced by Skanska was USD 1.06 billion (approximately RMB 7.5 billion).
The reconstruction target is the North Station No. 1 bascule bridge. The existing bridge was built in 1931 and consists of two rolling bascule bridges carrying a total of 4 railway tracks. It is the main corridor for Boston North Station commuter rail and Amtrak Downeaster trains crossing the Charles River. Approximately 200 trains pass through this corridor daily, serving more than 11 million passengers annually, while about 3,000 vessels pass through the waters beneath the bridge each year.
The original design scheme required first building a new lift bridge and a temporary railway bridge west of the existing bridge, demolishing the old bridge, and then building the remaining two new bridges on the east side. During construction feasibility analysis, the Skanska team found that the temporary railway bridge lacked mature experience from comparable projects, and that building a third bridge between two existing bridges in continuous operation was also constrained by construction space and site access conditions.
The joint venture and designer VHB subsequently used virtual design and construction technology to conduct construction feasibility analysis and proposed replacing the original three-bridge scheme with two new bridges. The adjusted two vertical lift bridges each have 3 tracks, increasing the total number of tracks in the cross-river railway corridor from the existing 4 to 6. This scheme reduces temporary bridge construction and demolition work and also lowers construction interference between existing railway operations and waterway traffic. According to Skanska, the scheme adjustment saves the project approximately USD 140 million.
In addition to the bridge structures themselves, the project also includes replacing approximately 8 miles (approximately 12.9 kilometers) of commuter rail track, installing 67 specially manufactured special track connection devices, upgrading signal and positive train control systems, and building a new railway control tower responsible for managing the approximately 200 trains passing over the bridge each day. North Station will also add a new Platform F and two additional station tracks, increasing the number of station tracks from the existing 10 to 12.
Construction began in May 2026, with an overall duration of approximately six and a half years, and is expected to be completed in 2032. During construction, the construction team must maintain round-the-clock operation of the cross-river railway and limit disruptions to Charles River navigation to no more than 5 days cumulatively over the entire construction period. The project plans to open one of the new bridges first in summer 2029, then continue to complete the other bridge and the related track and signal system cutovers.
The project also received support from a USD 472 million federal infrastructure grant approved by the U.S. Department of Transportation in 2024. Upon completion, the Boston North Station cross-river railway corridor will expand from 4 tracks to 6 tracks, with the replacement of the existing railway bridge and the station capacity expansion implemented simultaneously.
Related Products


Explosion-proof lithium battery dispatching monorail crane locomotive (permanent magnet frequency conversion integrated machine)
Xiangtan Hengxin Industrial Co., Ltd.


ZY(J)7(M) Sealed Type Electro-Hydraulic Turnout Machine
TAIYUAN CR JINGFENG EQUIPMENT TECHNOLOGY CO., LTD.


ERW Welded Pipe (Black Pipe and Hot-dip Galvanized Steel Pipe)
Handan Zhengda Steel Pipe Co., Ltd.
Wheel and Track Technology Business
Beijing Research & Design Institute of Rubber Industry Co., Ltd.