First Power Source Energized for 110 kV Supporting Project of Tianjin 117 Project in China

2026-11-28 18:02
Favorite

en.Wedoany.com Reported - On November 26, the first power source of the 110 kV business expansion supporting project for the "117 Project" in Tianjin, China, was successfully energized, providing reliable power support for the system joint commissioning and testing of the project's tower.

This project is an important power supporting project serving the "117 Project." Construction began on March 28, 2026. It is planned to build three 110 kV power sources, with a total cable route length of 14.9 kilometers, comprising four individual sub-projects covering cable line construction, substation renovation, protection system improvement, and other contents. In accordance with the city's deployment for key project construction, State Grid Tianjin Electric Power Company relied on a dedicated construction work mechanism, deepened government-enterprise coordination, proactively engaged with competent authorities including planning, traffic management, and urban and environmental departments in advance, efficiently advanced the approval process, continuously optimized the construction plan, and effectively promoted project construction.

In response to more than 30 high-risk operation points, including dense pipelines and construction involving high-speed railways, the project implemented segmented closed-loop control, accurately surveyed the distribution of underground pipelines, strengthened full-process inspections and hazard reviews, and strictly upheld the bottom line of construction safety. For construction activities involving railways, gas, and river channels, early intervention and synchronized pre-review were carried out to ensure orderly connection and efficient transition between operation areas.

Next, State Grid Tianjin Electric Power Company will continue to strengthen communication and coordination with the project user, respond promptly to user needs, further refine the tracking and support mechanism after energization, and ensure continuous and stable power supply. At the same time, it will accelerate the construction of the second and third power source lines to build a solid reliable power source foundation for the "117 Project."

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com