Wedoany.com Report-Dec.19, France's state-owned utility EDF has announced that it will limit the construction costs for six new nuclear reactors to 72.8 billion euros ($85.29 billion). The company emphasized its commitment to enhancing cost efficiency and accelerating the building process.

This updated figure, calculated at 2020 values, exceeds the initial projection of 51.7 billion euros made in 2022 when the project was first outlined. The six reactors will provide a combined capacity of approximately 10 gigawatts, helping to replace aging facilities and ensure long-term energy security. Nuclear power currently accounts for about 70% of France's electricity generation.

The revised per-reactor cost remains substantially below that of the recently completed Flamanville project, which totaled 23.7 billion euros despite significant delays. EDF plans to achieve savings through serial construction, targeting a roughly 30% reduction in expenses for the final unit compared to the first.

Xavier Gruz, executive director responsible for new nuclear plant project management, informed journalists that serial production will drive these improvements. Construction timelines are also expected to shorten progressively, with EDF drawing on successful experiences in China, a leading example in nuclear reactor development, to aim for a 70-month build duration.

"The gains we will have thanks to replication are significant," said Gruz, pointing to a targeted reduction of almost three years in construction time between the first in the series at Penly and the sixth at Bugey.

Gruz added that electricity demand is projected to rise substantially by the time the reactors become operational, driven notably by growing needs from data centers.

To support the initiative, EDF will benefit from a subsidized loan covering around 60% of the costs, repaid through contracts for difference based on the electricity produced. A final investment decision is scheduled for the end of 2026, with the initial reactor set to enter service in 2038.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com
Related Recommendations
Inyanga Marine Energy Group welcomes the Welsh Government’s Renewable Energy Sector Deal.
2026-03-20
2026 China's Local Blueprint: Shanghai, Sichuan, Hubei, Anhui, and Other Regions Include Fusion Energy Projects in Their 2026 Key Project Lists
2026-03-19
China Nuclear Environmental Protection: Concentrating Efforts on Reform for Breakthrough, Striving to Create a New Situation in the Nuclear Environmental Protection Industry
2026-03-19
Fu Liangqian Appointed as Vice President of the Southwestern Institute of Physics (SWIP) under China National Nuclear Corporation
2026-03-19
China Nuclear Power Equipment Holds Kick-off Meeting for the Promotion and Implementation of the "1455" Project
2026-03-19
Zhu Xiaoyan, Member of the Party Leadership Group and Deputy Director of the East China Energy Regulatory Bureau: Seizing Opportunities, Striving Diligently to Contribute East China Energy Regulatory Strength to Building a Strong Energy Nation
2026-03-19
CGNPC Environmental Protection Party Committee Deputy Secretary and General Manager Ren Junhua Meets with Southwest University of Science and Technology Vice President Fa Tao and Delegation
2026-03-19
China National Nuclear Power 5th Construction Company Selected as a National Intellectual Property Demonstration Enterprise
2026-03-19
2026 China-Korea Nuclear Energy Industry Exchange Seminar Concludes Successfully in Qingdao — Focusing on Supply Chain Collaboration and Overseas Expansion, Discussing New Opportunities for China-Korea Nuclear Energy Cooperation
2026-03-19
China's First Domestically Developed "Hualong One" Main Steam Release Isolation Valve Successfully Shipped to Guangdong Lufeng Nuclear Power Plant
2026-03-19
Lastest Bulletin
1
Inyanga Marine Energy Group welcomes the Welsh Government’s Renewable Energy Sector Deal.
2
2026 China's Local Blueprint: Shanghai, Sichuan, Hubei, Anhui, and Other Regions Include Fusion Energy Projects in Their 2026 Key Project Lists
3
China Nuclear Environmental Protection: Concentrating Efforts on Reform for Breakthrough, Striving to Create a New Situation in the Nuclear Environmental Protection Industry
4
Fu Liangqian Appointed as Vice President of the Southwestern Institute of Physics (SWIP) under China National Nuclear Corporation
5
China Nuclear Power Equipment Holds Kick-off Meeting for the Promotion and Implementation of the "1455" Project
6
Zhu Xiaoyan, Member of the Party Leadership Group and Deputy Director of the East China Energy Regulatory Bureau: Seizing Opportunities, Striving Diligently to Contribute East China Energy Regulatory Strength to Building a Strong Energy Nation
7
CGNPC Environmental Protection Party Committee Deputy Secretary and General Manager Ren Junhua Meets with Southwest University of Science and Technology Vice President Fa Tao and Delegation
8
China National Nuclear Power 5th Construction Company Selected as a National Intellectual Property Demonstration Enterprise
9
2026 China-Korea Nuclear Energy Industry Exchange Seminar Concludes Successfully in Qingdao — Focusing on Supply Chain Collaboration and Overseas Expansion, Discussing New Opportunities for China-Korea Nuclear Energy Cooperation
10
China's First Domestically Developed "Hualong One" Main Steam Release Isolation Valve Successfully Shipped to Guangdong Lufeng Nuclear Power Plant