en.Wedoany.com Report, At 22:00 local time on March 23rd, the Unit 2 gas turbine of the Uzbekistan Syr Darya Phase II 1600MW combined cycle project, constructed by China's Harbin Electric International (HEI), achieved a successful first ignition. This milestone marks another significant victory in the construction of this combined cycle power plant, which is the largest of its kind under construction in Central Asia. It also stands as one of the key achievements contributing to HEI's strong start in the first quarter.

Since the project's commencement, the Syr Darya Phase II project team has proactively tackled three core challenges: a tight schedule, long transportation cycles, and high management requirements. By thoroughly implementing Harbin Electric Group's directive of "ensuring performance on international projects," leveraging HEI's comprehensive capabilities in the EPC field for large overseas combined cycle power plants, scientifically organizing work processes, and coordinating multiple resources, the team has continuously overcome various risks and challenges. This effectively demonstrates the leading role of Harbin Electric Group as a "national team" in the equipment manufacturing industry.

Moving forward, the Syr Darya Phase II project team will use this successful ignition as a springboard to steadily advance unit commissioning and strive for the high-quality completion of the project. By delivering quality engineering and employing green technologies, the team aims to enhance the international influence of the "Harbin Electric" brand, allowing the light of clean energy to illuminate countless households along the banks of the Syr Darya River.