JSW Energy Synchronises Unit 2 of Utkal Thermal Plant
2025-01-25 10:54
Favorite

Wedoany.com Report-Jan 25, This boosts its operating thermal capacity to over 3 GW.

JSW Energy (Utkal) Limited, a subsidiary of JSW Energy Limited, has announced that it successfully synchronised Unit-2 of the Utkal Thermal Power Plant with a capacity of 350 megawatts (MW).

Following the acquisition of the plant under NCLT proceedings in December 2022, JSW Energy said it has fully revived and synchronised the entire 700 MW capacity at the Utkal plant in approximately 24 months.

Located at Jharsuguda district of Odisha, the plant runs on domestic coal and currently is not tied-up under long-term power purchase agreement.

JSW Energy’s locked-in thermal capacity so far stands at 7,458 MW. With the commissioning of Utkal’s Unit-2, the company’s operating capacity will increase to 3,858 MW.

This bulletin is compiled and reposted from information of global Internet and strategic partners, aiming to provide communication for readers. If there is any infringement or other issues, please inform us in time. We will make modifications or deletions accordingly. Unauthorized reproduction of this article is strictly prohibited. Email: news@wedoany.com