en.Wedoany.com Reported - On November 6, the City of Durham, North Carolina, USA, announced the construction progress of the East Durham Waterline Replacement Phase 1A, as the project continues to advance the installation of water supply pipelines, sewage networks, and stormwater drainage facilities, while simultaneously carrying out road restoration and river ecological restoration. From November 9 to 20, construction crews will conduct pipeline laying and supporting work in areas including Lincoln Street, Simmons Street, Colfax Street, Massey Avenue, and Spaulding Street.

Construction workers will continue installing water supply pipelines and carrying out pavement restoration on Lincoln Street, Simmons Street, and Colfax Street north of Linwood Avenue. Water supply pipeline and sewage network construction will also proceed simultaneously on the northern section of Spaulding Street. Upon completion of the related work, the East Durham water supply network will be gradually improved and the existing underground pipeline facilities upgraded.
Sewage network construction is mainly distributed in the vicinity of Grant Street, Massey Avenue, and Grant Park North. Specifically, sewage pipeline installation and ground restoration will continue in the pipeline corridor behind residences between Linwood Avenue and Price Avenue on Grant Street; sewage network construction will also be carried out on Massey Avenue between Lincoln Street and Grant Street. In the pipeline corridor between Lincoln Street and Colfax Street near Grant Park North, sewage pipeline installation, river ecological restoration, and construction area restoration are scheduled.
Construction workers will continue installing stormwater pipes on Lincoln Street in the area between Linwood Street and Simmons Street to improve the local stormwater collection and conveyance system. The project will also repair roads affected by construction and restore pavement in pipeline excavation areas.
During construction, the section of Massey Avenue between Lincoln Street and Grant Street will be closed to traffic. Portions of Lincoln Street, Simmons Street, Colfax Street, and Spaulding Street will be subject to road or lane closures as required by construction needs, with detour routes established to maintain access to residential and commercial facilities along the route. Park access will be maintained during construction at Grant Park North.
The project is managed by the City of Durham for construction management, with Moffat Pipe Inc. participating in construction. The content announced this time pertains to the two-week construction schedule for Phase 1A.
Related Products






Ultra-pure Ferritic Stainless Steel Products
Gansu JISCO Group Hongxing Iron and Steel Co., Ltd.

CITIC Heavy Industries Tunneling Equipment Tunnel Engineering Shield Machine
CITIC Heavy Industries Co., Ltd.

Industrial and Commercial Point-Type Gas Detector
Jinan Benan Technology Development Co., Ltd.

YHTank8400N Solvent-Free Liquid Epoxy Coating
JIANGSU YUNHU NEW MATERIAL TECHNOLOGY CO., LTD.