en.Wedoany.com Reported - On November 18, Canada's Talisker Resources announced progress on the construction of the ore sorting plant at its Bralorne gold mine in British Columbia. Earthworks for the first phase of the project have been completed, installation of power supply facilities has finished, and jaw crushers, cone crushers, and vibrating screening equipment have arrived at the mine site. Phase two earthworks and concrete foundation works are scheduled to begin in late November. The sorting plant is expected to commence initial operation in the second quarter of 2027, with full commissioning completed in July and August.

The mine site power supply system is equipped with two 1.5 MW diesel generators, with a total installed capacity of 3 MW and an output voltage of 600 V, capable of operating in parallel or independently. The underground mine steps up voltage to 4.16 kV through a 3,200 kVA transformer to distribute power to the underground substation and mining equipment. Surface power distribution facilities have been installed and can supply power to crushing, sorting, and other surface facilities. The system also reserves capacity for expansion with a third generator, with final commissioning planned for completion by the end of November.
Existing electrical facilities within the sorting plant construction area have been demolished. A new steel-frame tensioned membrane structure heavy maintenance workshop has been completed, and maintenance operations are being transferred to the new facility. The original maintenance workshop is scheduled for demolition within November. Phase two construction will include site cut-and-fill, foundation preparation, and installation of precast concrete components. Remaining tender documents for equipment installation, electrical, and mechanical works are planned for completion in December, with related construction and mechanical installation scheduled for implementation in the first half of 2027.
The core sorting equipment utilizes TOMRA XRT ore sorters, with factory acceptance testing planned for the second week of December and delivery to Canada in January 2027. Compressors required for the sorting system are expected to be delivered in the same period. Two steel-frame tensioned membrane structure buildings have been manufactured and are ready for shipment, with another two planned for completion of manufacturing and shipment in January 2027. The first batch of conveyors is expected to arrive on site in mid-December, with the remaining conveyor equipment to be delivered in batches during the first quarter of 2027.
Pre-commissioning will be carried out using existing ore stockpile materials before the sorting plant is put into operation. Ore enters the jaw crusher and is fed through a three-stage screening system into the XRT sorters. The separated gold-bearing material is then processed through cone crushers and ultimately stored in a covered material stockyard, while the rejected waste rock is transported via an independent conveyor system to the waste rock dump.
Related Products






1050-1750mm Steel Strip Single-stand Reversible Cold Rolling Production Line
MCC-SFRE HEAVY INDUSTRY EQUIPMENT CO., LTD.



Comprehensive Mining Automation Control System
Beijing Tianma Intelligent Control Technology Co., Ltd.

New Environmentally Friendly Green Potassium Salt Collector
Chonfar Engineering and Technology Co., Ltd.